I need Electricity at my home. I've applied for a connection on 17th November and today is 27th November how long it will take for a JE to approve it?
Everytime you're just giving me false commitments and I'm not getting any resolution from any portal why you guys are making me suffer. I've been waited 9 months to get electricity in my area and now I'm waiting to get a connection. Why you're JE ( Manoj Yadav) is not approving it? Ask him directly
Application Number: J2028059501
Application Date: November 17th 2026
Contact Number: 7607547105
Address: Plot No 37. Khasra Number 219 Vijay Nagar Malak Nilmatha Near Ganga Traders Crossing. 226002
District: Lucknow
Substation: Hariharpur
JE: Manoj Yadav (9415608061)
SDO: Devendre SDO (8004922010)
Everytime you people are saying the same that my compliant has been registered but no action has been taken and no help has been provided so far.
Even god can help the needy but UPPCL never helps anyone I'd say. Why you guys just raised a complaint and then keep it in Cold Baggage?
Corrupt Department. May be my next generation will get the electricity but I will not for sure and 1912 is useless to contact no resolution provided so far.
Application Number: J2028059501
Applied on 17th November
Need help you deaf and dumb people.
Now the Transformwr is On but still there is no progress on my Application Number: J2028059501.
I called twice to the 1912 helpline and they were talking so rude and badly no help provided.
I'll commit suicide if I'll not get connection I'm paying my Home Loan since 8-9 months. Please help. Don't ignore it
I can say it loud if our CM was @yadavakhilesh I must have not face these problems. Sir please help we' ve 10-15 houses ready in that area and everyone is waiting for Electricity and these UPPCL people and not even helping us. ππΌππΌππΌππΌππΌππΌ Really disappointed that getting Electricity in Lucknow is which is a capital of Lucknow is that difficult.