$ROG.ax | Busy month ahead at Innamincka, South Australia
✅ Yarrow North 1 re-entry - commencing October
✅ Willowie 2 - spudding within a week
✅ Yarrow 4 & 5 - awaiting stimulation
Red Sky holds 20% working interest
#energy#gas#ASX@SantosLtd
$ROG $ROG.ax | Yarrow 1 Online & Producing
🎯 Yarrow 1 well at Innamincka now online on schedule, following successful tie-in & commissioning📈 Expected to materially lift production & strengthen near-term cash flow 🔗 https://t.co/BYtPaz2VOn
#oilandgas#energy#resources#ASX
🚨 $ROG $ROG.ax | Drilling Commences at Killanoola-2 (KN2) 🚨 #spudding#energy#oilandgas#resources#ASX
⛏️ Drilling underway: marking a major step forward for Red Sky Energy
🧭 Project now moving from planning to full execution
⚙️ Condor Energy team operating efficiently on site
📢 Shareholder updates to follow as key milestones are achieved
🔗 https://t.co/u0LzyVHxXT
$ROG $ROG.ax | Red Sky moves even closer to drilling at Killanoola 🚀🚀 #energy#oilandgas
🌟DEM approval secured for drilling KN2 well
🌟Condor Energy mobilising third-party services, surface casing drilling set to start soon
🌟Big moves ahead!
🔗https://t.co/d8kG9Z1sZK
Drilling preparations well advanced at Killanoola (PRL-13).
✅ Rig and equipment mobilised
✅ DEM inspection completed
✅ Water monitoring approved
✅ Drilling program finalised
https://t.co/q3FGrgaJ29
Next step: DEM approval before KN2 drilling (~9 days).
#ASX $ROG #Oil #Energy #SouthAustralia
🚧 Progress at Killanoola 🚧
The KN2 well pad is now complete and ready for the next stage of operations
📍 PRL-13, Penola Trough, SA
📸 September 2025
$ROG $ROG.ax #RedSkyEnergy#oil#energy
$ROG $ROG.ax | 🚧 Red Sky Energy's KN2 pad construction at Killanoola continues to advance #energy#ASX
✅ Site has been levelled out and cut down
✅ Baseload fill now delivered and applied this morning
1/2
🚧 KN2 pad construction at Killanoola is advancing.
Cut & fill ✅
Compaction & levelling ✅
Crushed base next before rig mobilisation.
📍 MD Andrew Knox onsite monitoring progress.
📷 Photos below.
$ROG $ROG.ax #Energy
$ROG $ROG.ax | A major milestone at Killanoola! #Oil#Energy#ASX
KN2 well pad construction is underway, a key step for Red Sky Energy & shareholders. 🔥Our team is moving efficiently & respectfully, on track for drilling phase. 👍
Details: https://t.co/NJN1j0ncoX
$ROG Red Sky Q1 2025: Production, Progress, Potential #energy#oilandgas#Angola
✅ Yarrow 3 delivers $0.57M in gross production receipts YTD
✅ Yarrow 1 fracture stimulation completed; post-frac results show ~1.8 MMscf/d gas, with first gas targeted Q3
✅ In Angola Block 6/24, Red Sky booked 5.1 MMbbl (2C) and 11.0 MMbbl (2U) net resources
✅ Killanoola operations progressing with planned workovers and cost optimisation discussions underway
📄 Read the March 2025 Quarterly Report: https://t.co/LUwoTVPfvM
Watch our webinar w/ Red Sky Energy, feat. MD Andrew Knox. The webinar will commence with a presentation followed by a live Q&A.
Topics:
-Innamincka Project Performance & Outlook
-Killanoola Development Strategy
-Angola – Block 6/24 Opportunity
Register: https://t.co/fEOBETbaTx
$ROG Red Sky Energy unveils maiden resource estimates for Block 6/24, Offshore #Angola: 5.1M barrels (2C) & 11M barrels (2U) net to our 35% stake. Cegonha Oil Field set for rapid appraisal and development.
Learn more at https://t.co/R2llEOtlXB
#energy#oilandgas 🛢️📈
@PeterDutton_MP What are your plans for the gas industry? You don't see residents in the ME paying $2 a litre for petrol. Why are we paying 90c for auto gas?
$ROG Red Sky Energy Yarrow 1: Two frac stages completed ✅ boosting gas flow ⛽ JV to submit flowline build approval soon 🚧Flowline construction to begin Q2 2025, target online Q3 2025 🚀Details: https://t.co/UddwznrbLK #energy#oilandgas
Joint Venture partner Red Sky Energy $ROG says Santos $STO set to start fracture stimulation of Yarrow 1 well
https://t.co/dl8Il7l37U via @OffshoreTechMag#energy#oilandgas