Meanwhile the single narrow span carries two-way traffic for 50–60 villages — the main route to hospitals in Chitradurga, Davangere & Shivamogga, and it has caused repeated accidents. One ask: grant the blocks, launch the girders, finish the bridge. @AshwiniVaishnaw@GMSWR
A ₹7.5 cr railway bridge — fully sanctioned, girders & RCC boxes cast and lying in the open for 2+ years — with zero work done.
2nd span of RUB-88A, Hosadurga Road stn, Chitradurga. Only Mysuru Division's traffic block is pending.
@RailMinIndia@SWRRLY@DrmMys@AshwiniVaishnaw
On 24.04.2024 the Construction wing asked Mysuru Division to grant the 20 kmph caution order + line/power blocks to launch the spans (ref W.352/CN/BNC/I/HSD RUB/88A). The proposed June–July 2024 block dates lapsed. Two years on — no block, no work.