Construction of the new Gun Range data center at SpaceX’s Colossus 2 campus is progressing rapidly, with only a small section of the roof left to complete.
The facility is expected to be operational by the end of November.
#spacex#colossus#memphis
Updated map of all the land around the Colossus 2 campus that has been acquired by SpaceX-affiliated companies.
New is the property in the southwest, known as Project Mitchell.
SpaceX has also started buying residential properties in the southeast, near its power plant.
#spacex #colossus
Work is progressing on Spam, a former warehouse at SpaceX’s Colossus 2 campus that is currently being converted into a data center. It is getting a new roof, cooling infrastructure, and Megapacks, and is expected to be operational in December.
#spacex#colossus#memphis
Updated map of all the land around the Colossus 2 campus that has been acquired by SpaceX-affiliated companies.
New is the property in the southwest, known as Project Mitchell.
SpaceX has also started buying residential properties in the southeast, near its power plant.
#spacex #colossus
Updated map of all the land around the Colossus 2 campus that has been acquired by SpaceX-affiliated companies.
New is the property in the southwest, known as Project Mitchell.
SpaceX has also started buying residential properties in the southeast, near its power plant.
#spacex #colossus
Site preparation is underway at Tesla’s proposed $10.1 billion Project Crystal Sun solar manufacturing facility in Fort Bend County, Texas, just two weeks after the county approved tax incentives for the project.
#tesla#texas
The zoomed-in view of the Terafab site shows that the ground slab for the first building has been completed, while work has begun on the slab for a second building. Site preparation also appears to be underway for a possible third building.
#tesla#spacex#terafab
More tree clearing is underway south of the main Terafab site. The clearing farther east looks like it could be for power lines and other electrical infrastructure.
#tesla#spacex#terafab
The site plan for the proposed 747-acre AI data center campus in Cochise County, Arizona, shows more than 4,500 Megapacks across the entire campus.
#spacex#arizona
Plans have emerged for a 747-acre AI data center campus in Cochise County, Arizona, potentially linked to SpaceX. The project would feature nine large data center buildings, with an estimated power demand of 6 GW.
#spacex#arizona
Site preparation appears to have started for the second section of SpaceX’s solar cell factory in Bastrop, Texas, while construction of the first section is nearing completion.
#spacex#bastrop
The steel structure of the Optimus factory at Giga Texas has grown by another 65 meters and now spans about 495 meters from north to south (roughly 45% complete).
Additional earthwork is underway around the factory.
#tesla#optimus
Construction of Tesla’s Research Fab at Giga Texas is progressing rapidly, with major sections of the steel structure now going up.
Meanwhile, the trailer yard west of the site has been reduced in size to make more room for construction.
#tesla#terafab