This is the curb block from earlier. We have 5" for brick ledge and 4" for the floor to bare on. Again we custom cut this block at 11" down for the brick ledge
We cut the curb block down 11". We will screw an 11" tall plywood against the nailing flange that you see in the picture. So the floor sits on the top part and the brick ledge starts at the 11" down part.
I will take a picture after i pour
Another very successful pour. This house is in the town of Tecumseh.
Thank you Bill Sandre for giving us the opportunity for installing the ICF on this job
This the second house this year in which we did icf to the roof. We used the #energystick in both of these homes. They were very easy to insert. We used 1 electric heater to heat this house during the drywall phase. It was - 15Β°C for a week. Very warm in there.