Statnett🇳🇴 just froze new grid reservations for datacenters in Norway, until Aug 1, 2027 at the latest.
What it means for Nscale:
✅ Narvik phase 1 (230 MW) is already reserved, so VR depolyment should be intact.
❌ Most of Nscale's ~2,300 MW of reserved + requested Norwegian capacity is now frozen (Narvik phase 2, Korgen, Skien)
Contracted revenue: mostly OK.
Norwegian growth optionality looks more unreliable.
Compute is getting more scarce for every day that passes.
$IREN $NBIS $CRWV $nscale