Day 24: Perfecting the Gantt chart in Excel.
Made it dynamic with MAX, WORKDAY, IF and basic arithmetic, on my phone.
π΄ 2-day delay on a critical task: 20 β 22 days
π΅ Delay on a non-critical task: still 20 days
#ProjectManagement#Excel
@KennethArt_1@officialesther1 Building the Gantt on a phone is commitment. One idea for the next practice case: give the critical path tasks their own color and add planned vs actual dates next to each bar. Then simulate a two-day delay on task D and watch the finish date move.