Progress update, superstructure will be completed this week. Rear yard concrete scope will be completed end of the month. Pouring another section with the rear terrace this Friday. MEP roughing in full swing inside.
Decking installation will be completed today, bulkhead frame next. Rear yard wells and tank have been backfilled, forming shoring hexes for retaining wall footings. Will pour the roof and rear yard footings at the same time later this week.