Pouring concrete on Wa Pella. Placing the first layer of pavement on Andoa, Laurel, Corktree, Peachtree, Peartree, Basswood and Azalea Place. Pavement surface removal continues on Barberry, Hemlock and Westgate.
We’re finished with pouring concrete on Thayer, Maple, Elm and Louis. We’re pouring concrete on Wa Pella Avenue. We’ve also conpleted pavement surface removal on Andoa, Laurel, and Corktree. Roadway surface removal continues in Peachtree, Peartree, Basswood, Axalea and Barberry
The Resurfacing Program continues to move forward. We’re pouring concrete on Maple and Louis today, and doubling back to the first 11 streets to pick up curb gaps.
We’re continuing to make progress improving the streets. Pouring concrete today on Andoa, Laurel, Barberry and Hemlock. Removals are progressing also.
Today, we’re also proving pavement patches at various locations throughout the Village.
The 2026 Street Resurfacing project has been going for a few weeks. The first 2 weeks were just sawcutting, but removals and concrete pours have occurred this past week. Sidewalk was poured in Andoa and Laurel. Today, we’re pouring sidewalk on Corktree, Peartree and Peachtree.
Finishing up with concrete pours in a few locations along Robert and Palm today. Pavement grinding, patching and resurfacing is scheduled for next week.
We have been pouring sidewalk and curb and gutter over the last week or so. Today we’re pouring curb and gutter on the west side of Robert, and the north side of Palm.
We started work on Robert, between Cottonwood and Golf, and Palm, between Busse and Robert earlier this week. Removals on the east side of Robert are complete and we’re pouring sidewalk today.