OVM is a leading product supplier, solution provider and applicator in the field of Post-tensioning, Stay Cable system, Bridge Bearings & Expansion Joints.
{Update} Beginning of post-tensioning works for concrete slabs at “RAVILLE Tower” located in Cairo, Egypt using OVM BM15 Slab Post-tensioning system™.
#OVM
{Update} post-tensioning of concrete slabs continues on T02 & T03 (38 floors each!). Using OVM post-tensioning system, applied by STEELTEC (OVM certified applicator in Egypt).
#OVM
{Update} Post-tensioning activities continue at “The ARK” project in Cairo, Egypt using OVM PT system.
PILLAR, an OVM-certified applicator in Egypt, is responsible for supplying and installing post-tensioning system for the concrete slabs of buildings B03-6A &6B.
#OVM
“Unity is strength... when there is teamwork and collaboration, wonderful things can be achieved." – Mattie Stepanek
Photos from Tripoli’s Third Ring Road (TTRR) Project in Libya
#OVM
{Update} Construction continues at the 'Iconic Tower' in the Alamein Downtown Towers Project in #Egypt, using OVM Slab Prestressing System.
This impressive building has 68 floors and stands at 250 meters tall.
#OVM
{Update} We’re glad to announce the beginning of post-tensioning works for the concrete slabs of “Alamein Marina Towers T02 & T03” Project located on the Mediterranean coast in New Alamein City, Egypt.
#OVM
{Update} Completion of Post-tensioning works for concrete slabs of D02 and D02M Towers at “New Alamein Downtown Towers” Project using OVM Prestressing system.
#OVM
{Photo} from OVM specialized cable-stayed delegation field visit to the existing ‘Wadi Laban cable-stayed bridge’ in Riyadh, Kingdom of Saudi Arabia.
*OVM-KPT is ready and open to cooperate with all contractors bidding for this special project in KSA*
#OVM
{Update} OVM Prestressing system (M15A-37 strands) is being used to reinforce the Box section structure of the “Nile River Bridge”. a landmark structure of the “High Speed Rail- HSR” Project which is under construction between Red Sea and Mediterranean Sea in #Egypt.
{Photos} Application of OVM Prestressing system during the construction of “Al-Bidda Roundabout” Bridge which was successfully constructed in 2018 in Kuwait.
#OVM
{Photos} Application of OVM Prestressing system “OVM.M15A Anchorage Model- ETA Certified” during the construction of “Maintenance of 6.5 Ring Road” Project successfully completed in Kuwait.
Post-tensioning works was awarded and completed by OVM Agent in Kuwait: CANAR.
#OVM
{Photos} Application of OVM Prestressing system during the construction of “Roads and Bridges construction/maintenance for sections of South Surra area in the vicinity of Jaber Al-Ahmad Al-Sabah Hospital” Project which was completed in 2021 in Kuwait.
#OVM
{Update} Application of OVM Prestressing system at ‘Shuwiekh 30A Mall’ running project in Kuwait.
OVM Post-tensioning system has been supplied by OVM Agent in Kuwait: CANAR while post-tensioning activities are being applied by OVM Certified Applicator in Kuwait: HAJICO.
#OVM
{Photos} Application of OVM Prestressing System during the construction works of “EXPO Roads Network” Project in the United Arab Emirates, back in 2019.
-Client: The Roads and Transport Authority (RTA) – Dubai.
-Contractor: Larsen & Toubro.
-Consultant: Parsons.
#OVM