1/2 DOEL 2 The outage will start later than previously expected @2023-02-18 00:00:00+01:00 (was: 2023-02-11 00:00:00+01:00) and can commence production at full capacity earlier than previously expected @2023-03-22 00:00:00+01:00 (was: 2023-03-26
1/2 DOEL 1 The outage will start later than previously expected @2023-06-03 00:00:00+02:00 (was: 2023-05-27 00:00:00+02:00) and can commence production at full capacity earlier than previously expected @2023-07-05 00:00:00+02:00 (was: 2023-07-09