24 August 2026 Giga Texas Snapshots! Another hot morning here in central Texas but plenty of activity to see! As production ramps back up, we see a lot of transport activity took place over the weekend & more Cybercab Test Track testing too.
The 4 big construction sites are active today, with more grade work on Esther NE side by Tesla Rd, while the giant lined water retention pond on the SE side near the river is now about 1/3 lined with the waterproof membrane.
The E Advanced Chip Fab foundation work continues with most of the trenches filled in and many heavily reinforced concrete footings and foundation structures in progress. cortex 2 is prepping for more Megapack installation while the electrical,switchyard now has 4 new steel power pole base mounts nearly completed.
At the N Campus, the Optimus factory inexorably grows larger every day, with more steel arriving on site & what looks like foundations on the S end for possibly casting machines.