Project completed! Restricted access king post retaining wall completed in Sheffield for new client. Full package by DWM - design, supply and install - 9.0m long UC and PCC panel system to be clad in facing stone to match the conservation area.
Project update Wilmslow! 'flying shores' spotted in the suburbs. DWM extracting hydraulic props following installation of high level slabs allowing the ICF works to continue unhindered. #allinthedesign
Phase 2 of Mytholmroyd Railway Station for Casey Group starting with the fabrication and installation of a waler system to suit the drilled ground anchors. #deliveringprojects
Project update Wilmslow! Works almost completed with 36m concrete blinding pumped into place (photos pre blinding) ready to hand over next week to ICF contractor. Photos show the scale of the project! We have delivered all the works in house by our own team. #allunderoneroof
Project update Wilmslow, excavation works progressing in to the home straight even with the good old British summer! Concrete blinding next up then hand over to the ICF contractor. #allunderoneroof
Excavation works progressing well in Wilmslow given the current inclement weather. Drainage installed ready for final excavation works of the basement before blinding and handing over to the ICF contractor. #allunderoneroof
First 14.0m long ZZ26-700 piles being installed today as part of 240 linear metre permanent works sheet piled wall at Mytholmroyd Railway Station for Casey Group.
A lot a planning and preparation by DWM, MK Transport and Casey Group over the last few weeks but the RTG 16T is being delivered into Mytholmroyd today under road closure and police escort. Great team effort. Sheet piling works can commence next week #del…https://t.co/1tE36CwDjp
A lot a planning and preparation by MK Transport and Casey Group over the last few weeks but the RTG 16T is being delivered into Mytholmroyd today under road closure and police escort. Great team effort. #deliveryingprojects
Whilst on our other project in Wilmslow excavation works are progressing well, reduced level excavation in basement, ready for pool excavation work before lower level drainage works #allunderoneroof
DWM works this week finds us unloading piles in Mytholmroyd, external's at Alderley Park, retaining walls in Worsley and excavation in Wilmslow. #deliveryingprojects
Excavation works starting in Wilmslow. Hopefully the weather will hold! 2000m3 to excavate and propping to install to RC capping beam. #allunderoneroof
Short week this week and next week we are in June already! DWM found ourselves this week on two projects in Cheshire, one in Worsley and one in Mytholmroyd. #deliveryingprojects