Week of 5/25/26
• Bathroom countertop installation underway inside the Rock M Club
• Crews installing Tiger Den glass and placing limestone panels throughout the space
• Exterior progress continues with brick washing at Stair 4 &Area C.
•Paving work has begun in North Area B.
• Final punch-list and incomplete work items are now being addressed throughout Area A.
• Turf installation is underway inside the Rock M.
• Team store casework is being delivered and installed throughout the coming week.
Week of 5/18/26
• Crews will complete casework & floor polishing in Rock M Club field level & Levels 2 & 3 next week
• Masonry work set to begin inside the team store
• Ceiling instal on Level 3B continues to progress in the stands and suite areas.
• Wiring work for seating power on Level 2A ongoing
• Commissioning work beginning on the Level 3B ribbon boards
• High roof coping & Level 0 railings are now being installed
• Teams are beginning to address final incomplete work lists as preparations continue for game days
Pardon our progress!
The Memorial Stadium Centennial Project continues to take shape in Columbia. 🐯🏟️
Follow the latest construction and photo updates here:
🔗 https://t.co/E525kbYny2
Week of 5/11/26
• Major systems are coming online, with Elevator 5 set to open early next week, AHU 1 delivering conditioned air and temporary site power removed
• Level 1.5 work continues with startup of AHU 8 and testing, adjusting and balancing TAB underway for units 5 and 7
•Key interior finishes are progressing, including completion of the Level 3B ribbon board and Tiger Den ceiling.
• Additional finish work is advancing across the project, including installation of Rock M turf, limestone panels, ticketing-area masonry, and Level 2C carpet tiles