Burns & Mac has informed us that they will be starting the Unit 5 Gas Turbine this Sunday, April 29. The unit will be running in bypass mode, putting its steam to the Air Cooled Condensers,... https://t.co/UvwOa1IMC9
Burns & Mac has run the Auxiliary Boiler at 25% output all day today. This is the 1st of four load levels at which emissions data must be collected. Noise mitigation efforts have dampened... https://t.co/BoiQzKOCGu
Beginning tomorrow, Monday, April 23, Burns & McDonnell will be performing EPA mandated emissions testing of the plant’s auxiliary boiler. This testing must be performed 12 hours per day for... https://t.co/NmPnIgYP5J
On Sunday, April 15, Footprint Power Salem Harbor Development LP (“Footprint”) terminated its engineering, procurement and construction agreement with Iberdrola Energy Projects. Footprint... https://t.co/6kW35zCaWp