@GlobalinxDC finishing up our final conduit tie ins on Corporate Landing Parkway Virginia Beach VA. Globalinx will now have 3 diverse point of entry conduit systems coming into our Phase I Data Center that will be tied into MAREA AND BRUSA subsea cables.
@GlobalinxDC will be attending PTC in Hawaii January 19th-23rd. If you would like to schedule a meeting with us please email Greg Twitt CEO and Founder greg.twitt@globalinxdatacenters or George Tully VP of Business Development [email protected]
@GlobalinxSubsea our 2 X 600KW Generators have arrived. More pictures of the progress of our Phase I Carrier Neutral Data Center will be shared later this week. Very exciting time for Globalinx!!!!!!
@GlobalinxDC will be attending Capacity Europe in London this week Tuesday Through Thursday. If you would like to meet our CEO Greg Twitt and our VP of Business Development George Tully send me an email [email protected]
@GlobalinxDC getting our Data Center Campus conduit delivered and concrete being laid in advance of our 2 X 600KW generators arriving next week. Things are getting very exciting and coming along. More to follow in the upcoming week stay tuned!!!!!!
Globalinx Data Centers just completed installing our fire suppression throughout the facility and crac units arrived today. Globalinx will keep updating everyone on our progress as we complete Phase 1 of our campus.
Congratulations to our partner Telxius for the Marea subsea cable can now reach 200 TBS of capacity very exciting. The highest capacity cable to ever cross the Atlantic.
Lumos Networks getting their conduit trenched up Corporate Landing Pkwy. Globalinx Data Centers being a good partner allowing them to house their equipment at our Data Center and Subsea Cable campus
Northumberland-based @OsbitLtd, has completed a major upgrade to DeepOceanโs #subsea pipeline plough, to provide the AMP1500 with class-leading capabilities https://t.co/ybKLBCzqyR