REC’s subsidiary RECPDCL has handed over the Luhri Power Transmission Ltd SPV to Terralight Solar Energy Tinwari Pvt Ltd.
The ₹839.55 crore interstate transmission project will evacuate power from Sunni Dam HEP and Luhri Stage-I HEP in Himachal Pradesh.
Key works include a 400/220 kV GIS Nange Pooling Station and a 50 km 400 kV double circuit line connecting Nange to Koldam.
Indian Railways will fast-track production of 238 AC EMU rakes across ICF Chennai, RCF Kapurthala and MCF Raebareli.
The first rake is targeted for 2027 and the entire fleet by 2030, supporting Mumbai’s suburban network expansion.
AAI has invited bids for project management consultancy for a new integrated terminal building and allied works at Srinagar Airport, Jammu Kashmir.
Bid submission deadline: 21 September 2026.
89.5% physical work completed on the delayed 48 km Byappanahalli-Hosur doubling project.
Only 14 km (around 30%) has been commissioned so far.
A critical 61-metre open-web girder near Chandapura is scheduled for launching next month. Remaining works include track linking, electrification, signalling and telecom.
Heelalige-Anekal section is targeted for commissioning by January 2027. Full project completion is expected by early 2027 project cost has risen by around ₹190 crore from the original estimate.
89.5% physical work completed on the delayed 48 km Byappanahalli-Hosur doubling project.
Only 14 km (around 30%) has been commissioned so far.
A critical 61-metre open-web girder near Chandapura is scheduled for launching next month. Remaining works include track linking, electrification, signalling and telecom.
Heelalige-Anekal section is targeted for commissioning by January 2027. Full project completion is expected by early 2027 project cost has risen by around ₹190 crore from the original estimate.
AAI has invited bids for project management consultancy for a new integrated terminal building and allied works at Srinagar Airport, Jammu Kashmir.
Bid submission deadline: 21 September 2026.
The Cabinet Committee on Economic Affairs has approved ₹1,677 crore to expand the civil enclave at Srinagar International Airport.
A new terminal will raise capacity to 10 million passengers annually, with added aircraft bays, security barracks, and a 1000 car parking facility.
Indian Railways will fast-track production of 238 AC EMU rakes across ICF Chennai, RCF Kapurthala and MCF Raebareli.
The first rake is targeted for 2027 and the entire fleet by 2030, supporting Mumbai’s suburban network expansion.
A Vande Bharat train crossed the world’s highest railway bridge at nearly 100 kmph for the first time.
The speed limit on the 111 km Katra-Banihal section has been raised to 100 kmph, reducing travel time and improving connectivity to Kashmir Valley.
On June 6, 2025, PM Modi will inaugurate the Chenab Rail Bridge, the world’s highest railway arch bridge, and flag off the Katra Srinagar Vande Bharat Express. These milestones mark a major boost in connectivity and tourism for Jammu & Kashmir.
The 359 metre high Chenab Bridge, part of the USBRL project, showcases India’s engineering excellence, while the new Vande Bharat train promises faster, all weather travel between key destinations.
Ceigall India JVs won 5 road projects worth ₹2,423.70 crore for NH-913 (Arunachal Frontier Highway).
The projects cover about 278 km across Bile-Migging, Huri-Taliha and Sarli-Huri sections, with 48-month construction and a 5-year maintenance period.
The 2025 Maha Kumbh in Prayagraj, Uttar Pradesh showcased India’s ability to manage one of the world’s largest gatherings.
A 4,000 hectare temporary city, pontoon bridges, roads, sanitation, power, CCTV, drones and massive transport arrangements transformed the floodplain into a well-planned mega event visible even from space.
My best shot of the 2025 Prayag Maha Kumbh Mela from ISS. It is a once in a 144 year Hindu pilgrimage to sacred riverbanks in India and one of the largest events in the world, with millions of people in this single photo!
APSEZ is set to operate and mechanise two dry-bulk berths at Paradip Port for 30 years after quoting the highest royalty of ₹122.30/tonne.
The ₹982 crore project will add 18 MTPA capacity and expand APSEZ’s presence on India’s east coast.
The Centre approved ₹3,590.73 crore for the 82.58 km 4 laning of the Muzaffarpur-Sitamarhi-Sonbarsa corridor (NH 22) in Bihar under HAM.
It will improve connectivity to the India-Nepal border, reduce congestion and strengthen links to industrial, railway and logistics hubs.
UP Japan 🇯🇵summit : L&T semiconductor approved ₹500 crore investment in Noida, mostly towards fabless or other way, further details awaited. Firm has aquired assets from japanese firm Fujitsu electronics. They have an smaller setup at film city Noida
Jayakwadi Phase II:- Maharashtra Cabinet approved ₹6,477.88 crore for the project, including Majalgaon Dam and a 148 km right canal.
It aims to provide irrigation to 1.31 lakh hectares across 5 Marathwada districts, along with several reservoirs and water-lifting schemes.
Borivali-Virar Rail Expansion in Maharashtra
30% work completed on the ₹2,184 crore Borivali-Virar 5th & 6th railway lines project.
The project covers 26 km and is targeted for completion by 2029.
Additional tracks will increase capacity and better separate suburban and long-distance trains. Major works include 3 major bridges, 3 minor bridges, 1 ROB, earthwork and relocation of railway structures.
Land acquisition and clearances are progressing, with work underway at Dahisar, Mira Road, Bhayander, Naigaon, Nallasopara and Vasai Road.
₹9,450 crore investment approved for 4 multitracking projects across West Bengal, Odisha, Tamil Nadu and Andhra Pradesh.
Around 410 km of new rail lines will be added, targeted for completion by 2031-32.
Projects include 4th lines on Kharagpur-Bhadrak and Bhadrak-Haridaspur, and 3rd/4th lines on Gummidipundi-Gudur and Cuttack-Paradeep.
The project will produce 1.2 MTPA steel, create 5,000+ jobs, and is targeted to start commercial operations by 2029. It will also include a 145 MW captive power plant and several steel-making units.
Hon’ble Chief Minister Shri Suvendu Adhikari performed the Bhoomi Pujan and laid the foundation stone for Amit Metallics’ steel plant at Raghunathpur, Purulia.
With an investment of around ₹4,000 crore, the project will create 5,000 direct employment opportunities, marking a significant step towards industrial growth and economic development in Purulia.
BMC plans a ₹702.44 crore, 3.5-4 km underground pedestrian tunnel connecting the Mahalaxmi Racecourse & Science Centre Metro station area on Line 3 with the Worli Coastal Road promenade.
MMRCL will implement it under TOD guidelines, subject to final approval.
Odisha is targeting 3 more OSAT/ATMP semiconductor companies to expand its chip ecosystem.
The state already has 6 projects worth ₹14,795 crore under development and is focusing on mid-sized investments of ₹100-500 crore, PCB manufacturing, gallium nitride and silicon carbide.
Yes. @NHAI_Official is moving toward “Barrier-Free Tolling” so vehicles can pass through toll points without stopping at a physical toll booth.
@NHAI_Official says MLFF uses FASTag/RFID readers and ANPR cameras to identify vehicles and collect the toll without stopping.
A major milestone came on 1 May 2026, when NHAI rolled out MLFF at Choryasi Toll Plaza on the Surat–Bharuch section of NH-48 in Gujarat. Around 41,500 vehicles crossed the location on the first day.. #rslive