SECOND CYCLE 100-DAY CYCLE REPORT OF 2026
Cabinet received and noted an End of Cycle Report on the Implementation of Priority Projects for the 2nd 100-Day Cycle of 2026.
The 2nd 100-Day Cycle Programme which commenced on 25th May, 2026 and ended on 1st September, 2026, covered a total of 211 programmes and projects which were being implemented across 27 Government Ministries, Departments and Agencies in line with the National Development Strategy 2: 2026-2030 (NDS2).
The implementation prioritised projects of high impact, citizen-centric, low risk and rapid implementation. 136 projects (64.5%) of the 211 programmes and projects implemented were on target representing 80-100% including ICT deployment in schools, installations of manufacturing plant, secondary school infrastructure and commissioning of major highway bridges.
A total of 45 projects were within variance of completion of 61-79%, while 30 projects where below target scoring 40% and below of target completion. Cabinet highlights that 27 projects were being implemented in previously underserved areas including Mwenezi, Binga, Mlambapele, Tsholotsho, Gokwe, Mbire, Siakobvu, Kanyemba, and Nkayi.
Fifteen of these projects were on target at above 80% of completion, 10 projects were between 61% to 79% of completion, while only 2 projects were below target of completion.