The final stage of our Wryde scheme (phase 1 visible in the background) is the installation of this 3m diameter, 18m long culvert specially fabricated for us by Polypipe.
Another day. Another load of fly tipping at Willow Hall, Peterborough. This is one of two dumps of household waste within site of each other. Grateful for the assistance from local landowners too.
Well that’s a job very well done!!! Instillation of a twin penstock structure that will give the ability to divert water from one catchment to another during high water level events or in the event of a catastrophic failure of a pumping stations. #resilience
@cjd55yorkie Yes. This drain is in an area that has, until now, not benefited from an IDB drain in close proximity. This project will allow for more effective drainage in the West Side Marshes.
Replacing an old railway culvert that ran beneath the Spalding to March railway line. They certainly knew how to build things to last! Its demolition took some effort!