Surbiton Park Recycled Water Plant uses biogas to power on-site microturbines.
Optimal has replaced an end-of-life biogas compressor with a new Adicomp unit, installed with upgraded piping & testing. Final connections & commissioning are underway to restore reliable operations.
NSW mining and manufacturing: up to 50% co-funding (up to $10m) is available right now. The NSW Government’s Low Emissions Industry Program has a $40m pool and supports projects that cut at least 1,000 tCO2-e per year.
Link to grant: https://t.co/W98jw4RYr2
Optimal is officially entering the BESS market through a partnership with Delta Electronics. With one project already secured and a strong pipeline of additional opportunities, this marks a significant milestone in our company’s continued expansion within the clean energy sector.
There is a Capstone (@CGRNEnergy) microturbine in the classic 1950s superyacht, Istros, that Optimal has been servicing since 2023.
This was the first marine-approved microturbine ever installed on a superyacht, specifically engineered for maritime applications.
Optimal Group is proud to announce that we have commissioned a purpose-built biogas cogeneration plant for Saputo Dairy Australia (SDA) at its Allansford manufacturing facility.
#biogas#cogeneration#manufacturing#dairy
At the beginning of June this year, we had an internal information session to showcase our PowerPilot suite of control, monitoring, and diagnostics solutions to all employees at Optimal.
#control#monitoring#diagnostics#controller
Construction has begun on the KC8 carbon capture demonstration plant in Gladstone. The project, known as PACER, is set to showcase cutting-edge technology developed by @kc8capture, with Optimal playing a pivotal role in its execution.
#carboncapture#demonstrationplant#cement
Our PowerPilot systems were used to test the two C1000 turbines that we recently shipped to a community power project in the South Pacific.
The testing phase was successful, allowing us to resolve nearly all identified issues as we progress toward commissioning later this year.
The PowerPilot BlackBox and SecureLink will be integral parts of our control, monitoring and diagnostics solutions for future energy projects.
These solutions were developed in-house by Optimal, highlighting our significant R&D, product development and innovation capabilities.
We recently had the pleasure of welcoming staff from one of our clients in the South Pacific region to our Mulgrave facility for a comprehensive training program on plant and turbine operations.
#training#remotepower#testing#southpacific
The PowerPilot Commander, developed by Optimal, is now our standard control solution for all microgrid projects going forward. We are proud of our company’s growth and capability to develop highly complex products to complement the world-leading technologies of our partners.
Our distributor, @OptimalGroupANZ, will be participating at the Australian Renewable Heat Conference, August 26-27 in Sydney! Hear how you can utilize biogas as a renewable fuel in our microturbine solutions:
August 27th
🎤 Session 8
1:30-3:00 pm
🎤 Session 9
3:30-4:45 pm
We’re excited to share that the Rainbow Bee Eater (RBE) pyrolysis plant, which is currently under construction for a major glasshouse in regional Victoria, is now approaching the final stages of completion.
#pyrolysis#glasshouse#syngas#protectedcropping
We've partnered with DaRa Switchboards to deliver a main LV #switchboard for a remote #southpacific power project. Our engineers recently inspected and tested it to AS61439 standards before it's shipped for installation and commissioning.
Last week, we shipped 2 1000 kW @CGRNEnergy turbines to a new remote power station in the South Pacific region.
The plant will provide power to the local community and is being fully designed and built by Optimal Group.
#powerstation#communitypower#remotepower#southpacific
Late last month, Russell Burnett from Rainbow Bee Eater (RBE) presented at the Australia New Zealand Biochar Industry Group (ANZBIG) Conference.
#biochar#carbonremoval#syngas#boiler#pyrolysis
When RBE’s Holla Fresh ECHO2 Plant was being developed in 2021, it was featured in a Renew Economy article for its cutting-edge technology and environmental benefits.
Read the full article here: https://t.co/qYH9q4wWfI
After a successful FAT, the hydrogen C65 skid is finally heading to the customer’s testing facility in Western Australia.
The client is also looking forward to having us in WA for the commissioning in a few weeks.
#hydrogen#epc#engineering#energysolutions
Earlier this month, we completed FAT for a 100% hydrogen, Capstone (@CGRNEnergy) C65 hydrogen cogeneration skid with Optimal’s PowerPilot control systems at our Mulgrave facility. This is the third 100% hydrogen C65 delivered by Optimal and only the third of its type worldwide.