@PWD_Odisha officials led by Er Rathangdhar Rout, Chief Construction Engineer, Eastern Circle, inspected the construction progress of the 292m long High-Level Bridge over Budhabalanga River on SNKUBM (SH-19) road.
@PWD_Odisha officials led by Er Rathangdhar Rout, Chief Construction Engineer, Eastern Circle, inspected the construction progress of the 152.2 m long High-Level Bridge over Budhabalanga River on B.P.B.M Road and a 76m long High-Level bridge over Ura Nallah on the same road.
Er. Tushar K Panda, Chief Construction Engineer, @PWDBhubaneswar & District Judge, Khordha conducted a joint visit to finalize the location for shifting Sub-Collector & Tahasildar offices to OAT. Instructions were given to complete minor repair & renovation by mid-November.
Er Tara Prasad Mishra, Chief Engineer, DPI&Roads, inspected Jamujhadi-Basudevpur-Dhamara Road. Instructions were given to finalise culvert design proposed along the road & expedite work. Micro plans were discussed to address construction issues & target completion by March 2022.
Er Durga Charan Behera, Chief Construction Engineer with other @PWD_Ganjam officials inspected Old age home at Palur Hills, Berhampur. Main building (structural work) & Yoga Hall have been completed. The finishing work of project is underway & will be completed by December 2021.
The longest bridge in Odisha over river Mahanadi connecting Gopinathpur-Baideshwar in Cuttack District is getting ready. Today @Krishan_Kumar09, Secretary, @PWD_Odisha, along with senior officers, visited the site and reviewed its progress. The length of the bridge is over 3 Km.
Er Ashok Ku. Giri, Addl. Chief Engineer, Balasore Circle along with @PWD_Odisha official visiting to 100 Bedded M.C.H Building work & inspecting the LMO & PSA work at Bhadrak DHH site.
Administrative approval of ₹84.09 Cr has been accorded for construction of a 300-bedded New Building of District Headquarter Hospital, Bhadrak under @MoSarkar5T for the year 2020-21. The addition of a new building will give a boost to the health infrastructure in the district.
@PWD_Odisha officials inspected the foundation work of Regional College of Management, Khalikote. The project comes under @WorldBank supported Odisha Higher Education Programme for Education & Equity (OHEPEE) projects. It is expected to be completed by the end of 2021.
The civil work is likely to be completed by mid-July, and post-completion, partitioning work will be taken up for finishing the project by the end of this month.
Er. Sanjeeb Kumar Mohanty, Additional Chief Engineer, Balasore circle, inspected civil work of RT-PCR laboratory on the 2nd floor of the existing integrated lab at Bhadrak DHH. The lab plans to accommodate an autoclave room, mix room, doffing room as per requirement.
Administrative approval of ₹8.56 Cr has been accorded for improvement of Nuagaon (Rairangpur College) to Dundu via Jamda Road in Mayurbhanj District under the State Plan of @PWD_Odisha. The road will be widened and strengthened as part of the project.