The Red Salmon Complex is comprised of the Red fire burning on the Six Rivers National Forest and the Salmon fire on the Shasta-Trinity National Forest.
#RedSalmonComplex
Morning Update: 10-22-2020
Acres: 143,366 & 75%
**Red Flag Warning**
For the update, map, and smoke outlook, please go to: https://t.co/yq7Vpk1SAv
#RedSalmonComplex
Morning Update: 10-21-2020
Acres: 143,300 - 72% contained
For the full update, current map, and smoke report go to:
https://t.co/yq7Vpk1SAv
#RedSalmonComplex
AM Update: 10-18-2020
Yesterday, there was an intrusion into the restricted airspace over the fire by a drone.
To obtain a current update, map, and smoke report please go to:
https://t.co/yq7Vpk1SAv
Drones PSA https://t.co/KAx6sdTBQ2 via @YouTube
#RedSalmonComplex
October 17, 2020-Morning Operational Briefing with Al Ward, Operations Section Chief, California Interagency Incident Management Team 12
@SixRiversNF@Klamath_NF@ShastaTrinityNF
@theYuorkTribe @KarukTribe @hoopavalleytribe
@hoopaOES
https://t.co/mWHURFMjrQ
#RedSalmonComplex
October 17, 2020 Morning Operational Briefing - with Al Ward, Operations Section Chief, CAIIMT 12
https://t.co/mWHURG3UQq via @FacebookWatch
#RedSalmonComplex Daily Update 10-15-2020
Willow Creek, CA – Yesterday crews brought fire down to the South Fork of the Salmon River as planned.
More information on the Red Salmon Complex InciWeb page - https://t.co/yq7Vpk1SAv
@Klamath_NF@ShastaTrinityNF@SixRiversNF