Subcontractors are scheduled to place rebar for deck pour #14, continue work on the portals at Gate F and Gate G, and start work on the curbs around the promenade.
In the next few weeks, the contractor is scheduled to begin installation of the falsework and formwork along the agriculture building, begin work on the falsework in the middle of the lagoon, drive foundation piles for the promenade, & install the granite portals at Gates F & G.
This week the contractor continued installation of formwork and rebar for deck pour #11 on the north side of the lagoon. At the promenade, subcontractors continued the installation of the doors and electrical conduits at Gate F and Gate G.
Subcontractors are scheduled to place rebar and install conduits for deck pour #10 and deck pour #11, and continue work on the curbs around the promenade.
Over the next several weeks, the contractor is scheduled to continue work on formwork along the Ferry Building, driving foundation piles in the lagoon, and the installing the portals at Gate F and Gate G.
The subcontractor began installing the door frames on the portal and another subcontractor began test fitting electrical to the structure. With the pile driving season open, the contractor continued pile driving activities.
Over the next several weeks, the contractor is scheduled to continue installing formwork along the Ferry Building and driving foundation piles in the lagoon.
The subcontractor continued installing rebar for deck pours #10 and #11.
A total of eight foundation piles were driven this week. Offsite, the floats and gangways continued the voyage to Alameda.
This week the contractor continued installation of formwork for deck pours #10 and #11 and falsework for the step up in deck pours #11 and #12 on the north side of the lagoon.
Offsite, the floats and gangways are being prepared for transport to California through the Panama Canal, while metal fabrication will continue in Alameda.
Subcontractors are scheduled to place rebar and install conduits for Deck Pour #10 and Deck Pour #11, and continue work on the curbs around the promenade.