D) −€30k.
Cost variance is earned value minus actual cost: 180 − 210 = −€30k. Negative means over budget.
The trap is B. −€20k is the schedule variance: earned value minus planned value.
It's one of the 90 IPMA D questions we've written for https://t.co/TuxMWD4kVu.
IPMA Level D practice question:
Planned value is €200k, earned value is €180k and actual cost is €210k. What is the cost variance?
A) +€30k
B) −€20k
C) +€10k
D) −€30k
Answer in the reply. Pick yours first.
The real argument was who gets to do it.
Option A: only with the sponsor's approval.
Option B: the project lead alone, with a required reason.
We picked B, even for strict projects. The lead owns the plan, and re-releasing it goes through approval anyway.
One project in our planning tool forecast an end date in 2070.
Not a bug. It was imported with work packages from 2021 that nobody had touched since. The plan itself was wrong, and change requests can't fix a plan that's wrong as a whole.
So we built "back to planning": the project lead takes a running project back into planning, reworks it freely and releases it again as a new baseline.
Nothing recorded is lost. Booked hours, progress and earlier baselines all stay.
560 commits in four weeks, on one product.
I run Agile Coderz, a small software company in Vienna. From today I'm building our products in public: what we ship, what we decide, and what breaks.
First up: https://t.co/TuxMWD4kVu and projectbox.
New side project: Circular Bricks.
Falling bricks on a circle. Gravity points down, so you turn your phone to turn the ring. Fill a ring to clear it.
Free on iPhone. No ads, no account, no tracking.
Two weeks from first line of code to the App Store.
https://t.co/hCrM4mhkcg