@seraleev I called support, they said it had to go to a senior. Response in 48hrs. That was weeks ago.
Opened new tickets while poking the old ones. Has to go to a senior.
A month later, nothing.
Some Signed AI Server Orders Rose 45%: The Contract Isn't a Price Cap on AI Capacity
The reports describe server vendors changing prices on deals that buyers had already signed. That matters more than an ordinary list-price rise. A list-price rise affects future purchases. A change to a signed order affects capacity that buyers have already planned, financed and in many cases sold on to their own customers.
A 45% increase on some orders is large enough to change the economics of an AI deployment. A cloud provider, enterprise or research lab that sized its budget, its loan or its customer pricing on the original quote now needs more capital for the same hardware, or must accept less hardware for the same capital. The practical lesson for anyone buying AI capacity is that a signed price for unshipped hardware may work more like an estimate than a ceiling.
The timing gives the story a quick public test. Dell and HPE both report results soon, and analysts will look for whether higher prices show up as better margins, as order delays, or both.
What they're not saying:
• Scope: Dell, Lenovo and the other vendors have not said how many signed orders were repriced, which product lines were involved, or whether the 45% figure is typical or the highest case.
• Contract basis: The vendors have not said which contract terms allow repricing after signing, such as component-cost clauses, expired quote windows or changed delivery dates, or whether customers could cancel without penalty.
• Cost drivers and impact: The vendors have not broken down which components rose (memory, storage, networking or accelerators), and Dell and HPE have not yet said how the increases affect AI server margins, backlog or expected shipments.
The part that didn't make the press release 👇
IES's Backlog Doubled to $4.96B: AI Data Center Growth Is Gated by Crews, Not Orders
IES Holdings closed fiscal 2026 with record results: full-year revenue of $4.48 billion, up 33%, and operating income of $605.7 million, up 58%, according to the results release the company filed with the SEC. The fourth quarter accelerated further, with revenue up 55% and operating income more than doubling. IES credited data center demand for the growth in its Communications, Commercial & Industrial and Infrastructure Solutions segments.
The more telling figure is the order book. Backlog more than doubled over the year to about $4.96 billion, while revenue grew by a third. Work is arriving faster than the company can perform it. IES’s own explanations for its growth repeatedly point to capacity and trained workforce as the inputs that let it capture demand, and its largest strategic move, the DBM Global acquisition, buys about 4,000 skilled employees and more than two million square feet of facilities.
At the same time, the board added $350 million to the buyback, and an 8-K filed November 20 shows new cash bonuses and stock-price-based awards for senior executives. Together these signal management’s confidence that the backlog will convert into cash. Whether margins hold once the favorable quick-turn projects of the second half roll off is the open question.
What they're not saying:
• Conversion timing: IES has not said how much of its $4.96 billion backlog, or DBM’s $2.6 billion, it expects to recognize as revenue in fiscal 2027, and it gave no numerical guidance beyond expecting “continued strong organic growth.”
• Workforce capacity: Outside the roughly 4,000 employees acquired with DBM, the company has not quantified headcount growth, wage pressure, or whether crew availability is affecting which projects it bids on.
• Customer concentration: IES’s results announcement does not identify its data center customers or how much revenue its largest clients represent, which matters when one end market drives most of the growth.
What I'd want answered before calling this a win 👇
ASE's NT$248.9B Test Site Treats AI Chip Supply as More Than a Wafer Problem
ASE has launched the second and larger phase of a testing cluster in Renwu, Kaohsiung. The NT$248.9 billion J block investment is a planned commitment announced at the groundbreaking, not a single contract, and it focuses on advanced testing and automation for high-performance chips: the processors used in computing and data centers. Chief executive Tien Wu said at the ceremony that “the new AI wave has only just begun,” adding that demand for high-performance chips and advanced testing will keep rising.
The significance lies in where the money is going. Discussion of AI chip supply usually centres on wafers, the silicon discs that foundries print chips onto. ASE, the largest outsourced packaging and testing company, is committing roughly NT$366 billion across two adjacent blocks to the step after that: verifying that finished chips work. Combined with the K block, that is a bet that AI chip output will scale only as fast as test capacity does.
The caveat is timing. The J block completes in phases in 2028 and 2029, so this is capacity for the next stage of the AI buildout, not relief for today’s, and ASE has not named customers or contracted volumes behind it.
What they're not saying:
• Customers and commitments: ASE has not named customers for the J block or said whether any of its capacity is contracted or prepaid.
• Financing and phasing: ASE has not said how Taiwan Fore Electronics will fund NT$248.9 billion, how the spend splits between buildings and test equipment, or how much lands in 2028 versus 2029.
• Scope of advanced testing: ASE has not specified which test stages the plant covers, such as wafer probe, final test, burn-in or system-level test, or how it connects to ASE’s advanced packaging lines.
The questions this raises, and who isn't answering them 👇
Akamai's $2.5B Raise Says Edge AI Clouds Are Limited by What They Can Build
Akamai has raised $2.5 billion in low-coupon convertible debt, meaning bonds that investors can later swap for stock if the share price rises enough. The money serves two jobs: refinancing a 2027 maturity and paying for the build-out of CIS, the company’s cloud computing business that now sells capacity for AI workloads alongside its long-established content delivery and security services.
The pairing matters. Chief Financial Officer Ed McGowan framed the raise around executing on “existing customer commitments” and said that as revenue from “committed Cloud Infrastructure Services contracts ramps,” Akamai expects a significant increase in EBITDA margins (earnings before interest, taxes, depreciation and amortization, a common proxy for operating profitability) and operating cash flow beginning in 2027. A company turning away business while borrowing to deliver contracts it has already signed is describing a supply constraint, not a demand problem.
That has implications beyond Akamai. If a provider of Akamai’s scale is capacity-limited, the power and facilities squeeze that has defined hyperscaler expansion is also setting the revenue ceiling for the next tier of cloud and edge providers.
What they're not saying:
• Declined demand: Akamai has not quantified the AI business it is turning away, nor said which regions, customer types or workload sizes are affected.
• Power and capacity: Akamai has not disclosed how many megawatts of power it has contracted for CIS, how much is already energized, or when additional capacity is scheduled to come online.
• Use of proceeds: Akamai has not specified how much of the roughly $2.2 billion remaining after hedging costs will go to CIS capital expenditure versus retiring the 2027 notes, or the total value and duration of the committed CIS contracts it expects to ramp in 2027 and 2028.
The questions this raises, and who isn't answering them 👇
ChronoScale's $7.5B AI Deal Rides on 65 Ordered Megawatts, Not Odessa's 350
The headline number is up to $7.5 billion over six years. The structure ChronoScale disclosed in its announcement and 8-K is narrower than the campus it sits on. The contract value attaches to the initial deployment, which is the 65 MW already ordered. ChronoScale holds only a right of first offer on the remaining 285 MW. That capacity becomes real only if the customer orders the second and third phases and the site secures the power, permits and capital to build them.
The financing follows the same pattern. Here is how the $750 million headline breaks down:
• $153.0 million in cash from about 19.1 million shares sold at $8.00, which closed on November 18.
• A convertible note issued to Applied Digital, which covers part of the $250 million equity component.
• A $10 million first call on the preferred facility.
• The other $490 million of that facility, which is a conditional right to draw over four years.
ChronoScale says its common equity proceeds fund only the initial portion of its $390 million contribution to the partnership.
The result is a contracted, partly backstopped first phase attached to a much larger option. For developers, GPU suppliers, lenders and investors, the operative question is whether 65 MW can be powered and delivered in the first half of 2027, because that capacity is what earns the contract value.
What they're not saying:
• Who the customer and backstop are: ChronoScale has named neither the frontier AI lab nor the investment-grade technology company providing credit support. It has not quantified what “a substantial portion” of the first phase means in dollars or megawatts.
• Power for phase one: ChronoScale has not disclosed the utility, the interconnection status, any onsite generation, or the energization date for the 65 MW scheduled for the first half of 2027. It has said nothing about permits or power for the remaining 285 MW.
• GPU supply and delivery terms: The company has not named its GPU supplier or delivery schedule. It has not disclosed what the GPU services agreement provides if phase one slips, such as penalties, termination rights or price changes.
The part that didn't make the press release 👇
@thesimaximalist There are all kinds of theoretical accelerators. Or you're at risk without backups, or maybe the building isn't done because these things are staged so you dont pay for the 90th percent completion when you're only at 65th.
Heard a lot of these, haven't seen many that work out.
Homer City Sets 2 of 7 Turbines; Its 4.4 GW AI Power Date Hinges on Five Deliveries
Homer City Generation, its construction partner Kiewit, and turbine supplier GE Vernova have moved the Homer City Energy Campus from site preparation into heavy equipment installation. Two 7HA.02 turbines, GE Vernova’s large, high-efficiency heavy-duty gas turbine class, are now set on their foundations, and the first half of the heat recovery steam generators (HRSGs) is in place. HRSGs capture hot turbine exhaust to make steam for a second, steam-driven generator. That combined-cycle arrangement is what lets a gas plant squeeze more electricity from the same fuel.
The milestone matters because Homer City is one of the clearest tests of whether new gas generation can be built at the scale and speed that data center growth, much of it driven by AI, now demands. At up to 4.4 GW, roughly the output of four large nuclear reactors, the campus is reported to be the largest gas-fired facility under construction in the U.S. The project’s schedule is no longer about whether it will be built. It is about whether the remaining five turbines and the second half of the HRSGs arrive in time to hold an early-2028 first-power date.
What they're not saying:
• Who buys the power? Homer City Generation has not disclosed contracted customers, offtake agreements or data center tenants for the 4.4 GW, or how much of the output is committed.
• First power versus full output: The developers cite early-2028 first power and a 2028 commercial power target, but they have not said how many of the seven units will run at first power or when the full 4.4 GW will be online.
• Delivery schedule detail: GE Vernova and Homer City Generation have not published a unit-by-unit delivery schedule for the remaining five turbines or the second half of the HRSGs, or said how much schedule buffer exists.
The questions this raises, and who isn't answering them 👇
Digital Realty's $10B Japan AI Plan Maps Only 220 MW of a Near-4x Footprint
Digital Realty is putting a ten-year, $10 billion marker down in Japan, aimed squarely at AI workloads. The near-term evidence is concrete: NRT14, which opened in April 2026 as one of Japan’s early NVIDIA DGX-Ready facilities, supports 150 kW per rack, and KIX15 near Osaka is being built with hybrid air and liquid cooling for high-density AI hardware sold to hyperscalers and cloud providers.
The headline ambition, however, runs well ahead of the disclosed pipeline. Nearly quadrupling a 170 MW base implies a footprint on the order of 600 MW or more; the projects identified so far take the portfolio to roughly 220 MW. That makes the plan less a construction schedule than a long-dated commitment to secure sites, power and customers in Tokyo and Osaka over the coming decade.
For customers, it signals more AI-grade capacity in Japan’s two main hubs, though most of it is years away. For investors, the measurable checkpoints are KIX15’s Q4 2028 opening, NRT14’s lease-up, and when the sites behind the remaining growth are named.
What they're not saying:
• Whose capital, and how it is financed: Digital Realty and Mitsubishi have not said whether $10 billion is Digital Realty’s share or the joint venture’s total spend, nor how it will be funded across debt, equity or partner contributions.
• Sites beyond 220 MW: The companies have not identified where the bulk of the near-fourfold growth will be built, which project besides KIX15 lifts the portfolio to 10 facilities, or the phasing between now and the mid-2030s.
• Power and permits: No grid connection agreements, power procurement terms or specifics of the renewable energy initiatives have been disclosed for KIX15 or later phases.
What I'd want answered before calling this a win 👇
Micron's $14.6B China Tie Means Export Law, Not Orders, Decides Where Its AI Memory Goes
Washington has closed another route by which Chinese buyers could reach advanced US chips, and markets repriced the AI hardware chain in response. Micron is the clearest exposure: it has $14.6 billion in China-linked revenue, and for whatever share of that the tightened rule reaches, the deciding factor is now a US export license rather than customer demand.
The timing sharpens the point. Days earlier, CoreWeave reported a $132.5 billion revenue backlog, more than 4.6 gigawatts of contracted power and raised guidance — evidence that AI infrastructure demand outside China remained strong. The selloff reflects a change in who is allowed to buy, not a reported fall in how much buyers want.
For data center operators, cloud buyers and investors, the practical takeaway is that policy risk now sits alongside power, supply and financing as a variable in AI infrastructure planning. Nvidia’s leadership change adds a second uncertainty ahead of its November 17 earnings report.
What they're not saying:
• Micron has not said what share of its $14.6 billion in China-linked revenue falls under the tightened rule, whether it will seek licenses, or whether restricted volume can be redirected to other customers given tight memory and storage supply.
• AMD, Broadcom and Monolithic Power Systems have not quantified their own China exposure under the new rule or said whether guidance is affected.
• CoreWeave and Nebius have not said whether the rule touches any customers or deployments; for CoreWeave, that includes its more than 1.3 gigawatts of contracted international power in markets such as India and Indonesia.
The quiet part of this story 👇