@sepalghar sir,
The work of pole replacement has been allotted to agency M/S Snehal https://t.co/0Bh9xymS8y Dahanu & the work will be completed within 15 days
@MSEDCL@sepalghar @sevasaivirar complaint of Ratnesh mothe dt. 26.06.2018
Sir,
the work is allotted to M/S Snehal Electric co. Dahanu & the work will be completed within 7 days
@sepalghar COMPLAINT OF RATNESH MOTHE DT. 26.06.2018
SIR, The work is allotted to agency M/s Snehal Electric co. dahanu and the work will be completed within 7 days
@sepalghar Sir, 132 KV Boisar-II line trip on overload on dt. 19.06.2018. Due to these all feeders emanating from 132/33 KV EHV S/S were interrupted. 33 KV Genesis supply is not available from 23.07 to 12.00Hrs,33 KV Allyali from 23.07 to 12.08 Hrs and 33 KV Palghar from 23.07 to 00.00 Hrs