•Building structure:complete to the top level;
•Wall construction: ground floor 50% and first floor 25%;
•Windows: installation commenced;
•Building services: well advanced;
•Lifts: delivered to site;
•Joinery cabinets: 25% delivered to site;
#Victory#apartment
Victory Brunswick East Progress Updates Part 2:
• Second floor – awaiting concrete stressing prior to stripping commencing
• Third floor – concrete poured
• Fourth floor – east side concrete poured, west side to be poured early next week
#victory#goldfieldgroup#melbourne
Victory Brunswick East Progress Updates Part 1:
• Basement L1 and L2 – services rough in ongoing
• Ground floor – frame work and wall lining ongoing, services rough in commenced
• First Floor – stripping ongoing
#brunswickeast#victory#melbourne#apartments#goldfieldgroup