#Hyderabad :
Two students were arrested by the RGIA Airport police on 17th Feb, for performing dangerous #Stunts (#CarStunts) with #BMW and #Fortuner luxury cars on #ORR stretch near #Shamshabad in the early hours of 9th Feb.
The video had gone viral on social media platforms and it raised #RoadSafety concerns among the motorists.
They removed the number plates during stunts, the RGI Airport police traced the cars with the help of CCTV and after identifying the drivers caught them. The luxury cars were also seized.
The arrested are Mohammed Obaidullah (25), a resident of Rajendranagar and Zohair Siddiqui (25), a resident of Malakpet on 9th February went on the ORR Shamshabad and were doing stunts in two different cars.
The act was captured on the closed circuit cameras installed on the ORR stretch.
@annamalai_k Mr.5 thozvi Annamalai, there is a lot of difference between the Sanadana dharma and Hindu Dharma. Like between Sangi and Sanniyasi. 1st do some good things to the ppl and get some good will. Then speak about others.
@TelanganaCMO@GHMCOnline just https://t.co/e5UzlbMs16 N-conversion hall, there are many buildings that were constructed in the FTL area. Seems they built a mini city. What about those encroachments?? Or you are targeting only @iamnagarjuna
Explained: N Convention demolition
Relief to Actor @iamnagarjuna as High Court of Telangana has given interim stay on the demolition today afternoon. But the point is the demolition is already done.
Official statement from HYDRAA—
- In 2014 HMDA had issued the preliminary Notification for Tammidikunta Lake with regard to Full Tank Level (FTL) / and Buffer zones. In 2016 the final notification was issued.
-After issuing the preliminary notification in 2014, M/s N – Convention approached the High Court. The High Court then directed that due process of law should be followed in the respect of determination of FTL.
-Accordingly FTL survey was conducted in the presence of petitioner M/s N- Convention and survey report was communicated to them. M/s N – Convention then approached the Miyapur Addl. District Judge Court on the survey report in 2017. This case is pending. There are No Stay orders from any Court.
-M/s N – Convention has clearly manipulating the Systems & Process and continuing their commercial activity through the Unauthorised structures built in the FTL & Buffer Zones., M/s N- Convention has encroached 1 – Acre 12 guntas in FTL and 2 Acres 18 guntas in Buffer zone and raised unauthorised structures, GHMC has not given any building permission to M/s N – Convention.
-M/s N – Convention has tried to regularise the unauthorised structures under Building Regularisation Scheme (BRS) but was rejected by the concerned authorities.
Due to the unchecked encroachments in and around Tammidikunta Cheruvu and the connecting Nalas the area around Madhapur, Hi Tex are facing serious water logging issues. The lower reaches of the Tammidikunta cheruvu are being inundated during heavy rains regularly as the cheruvu capacity to hold water has shrunk by more
then 50 - 60%. Many houses of lower and middle class people are getting submerged in these lower reaches resulting in severe loss of property to them.
-M/s N – Convention is built in the FTL / Buffer Zone and has no building permission what so ever.
-After following the due process, the official’s of HYDRAA along with irrigation, Town planning, revenue etc has completely demolished the structure.