Road carpeting work has been initiated at PWD underpass East ramp.
After carpeting, traffic will divert on East side (as per plan approved by traffic police) and work on underpass shall start accordingly.
#IslamabadExpressway
⚠️ Due to construction work on #IslamabadExpressway, gas supply to neighbouring areas will be disrupted on Friday, 26th February & Saturday, 27th February. To avoid any untoward incidents, please make sure to keep all gas valves shut.
SAPM on CDA Affairs @AliAwanPTI visited the construction site of PWD interchange at #IslamabadExpressway today. He directed CDA to complete the project as soon as possible.
The Korang Bridge project is estimated to take 15 months to be completed while the PWD Interchange will take around 7 months.
#CampaignforIslamabadExpresswayExpansion
The Construction of Korang Bridge and PWD Underpass project will also be executed by CDA in 15 and 7 months respectively. The project will be funded through Public Sector Development Program.
PM @ImranKhanPTI performed groundbreaking of various development projects in Islamabad earlier today, including Korang Bridge & PWD Interchange on Islamabad Expressway.
Chairman CDA Amer Ali Ahmad briefed the PM on the projects.
#CampaignforIslamabadExpresswayExpansion
PM @ImranKhanPTI is likely to inaugurate the projects of Korang Bridge & PWD Interchange on June 30.
PM has also directed CDA to complete these projects as early as possible.
Read: https://t.co/0e0hgYfCOL
Renders of the new Korang Bridge and PWD Underpass / Interchange on Islamabad Expressway. Construction work is to begin soon InshaAllah.
#CampaignforIslamabadExpresswayExpansion
UPDATE: Bids for Korang Bridge and PWD Interchange accepted. Contract for both projects awarded to Zero Point Interchange builder.
https://t.co/PlfZVGP1xR
#CampaignforIslamabadExpresswayExpansion