@pankowbuilders The interior spaces at 1951 Harbor Bay Parkway have really come together over the past few weeks. Pankow and our Trade Partners are rounding out the year by starting the punch list phase. Very proud of the Pankow project team!
Final slab-on-metal-deck pour today for the 1951 Harbor Bay Parkway project. Another milestone achieved on schedule. Great teamwork and execution. Kudos to Pankow Concrete! @pankowbuilders
The 1951 Harbor Bay Parkway project raised the celebratory final steel beam on Wednesday January 7, 2021. While this ‘topping off’ celebration was scaled back, we appreciate the teamwork and effort from all project participants no less. @pankowbuilders @brick_arch @TippingSE
@pankowbuilders Pankow VDC Manager Lou Varni taking it to the next level and including a scaled human figure in a BIM model to identify and share constructibility concerns with the design and construction team. #PankowVDC#allday#slowclap 👏
@pankowbuilders UCSF CSB Retrofit: Pankow field crews enjoying some well deserved BBQ on a Friday! The schedule demands and tight quarters of the project have proved challenging, but this team of carpenters and laborers has melded together and taken the challenge head on!
@pankowbuilders Tower crane dismantle at the Van Ness MOB over Easter weekend. Big thanks to Gerald Tomeo, Jim Norris and our union laborers for their time. Another successful Sheedy operation.