I still think Tera fab has no clarity for buildout and development. You can't do both cutting edge memory and logic development at the same time, and packaging on top of that. Even for memory, you have NAND Flash and DRAM and HBM. No one can truly focus on all. The biggest winner from Terra fab buildout will be the equipment providers (AMAT/LAM etc). They will realize 4-5 years in, it was a complete disaster to even think they can embark on this and. You might be able to hire the top executives, but everyone else below, tough luck.
Let's say that even if Tesla somehow has a cutting edge AI chip, they ain't going to get capacity from TSMC and the Memory fabs any time soon. Capacity is booked out so far out, and even if you wanted it, fabs would only give a tiny portion to you to prevent angering their existing customer. Elon's plan about building terra fabs for chips manufacturing is totally implausible even with a trillion dollar dumped at the problem.
@jiahanjimliu π―, GB300s will be the main ramped up chip delivery for H2 2026, into 2027. VR earliest still H1 2027, but I think likely H2 2027. Small batches not going to cut to fill up 300-500MWs in SW in H1 2027 π
I think another great benefit of colocation is that the HS would be able to provide the GPUs on time. Because their bottleneck is lack of DC power coming online in 2026. But they had been in the queue for GB300s much earlier. Would have solved the current AI GPU delivery delays IREN is facing.
@jiahanjimliu @xiaochuan8688 Yep, thought IREN would have signed more contracts by now and ramping faster. Flywheel not really turning, and won't be any time soon. Guess have to patiently wait till Q4 before any real re-rate will happen.
Which is a problem for IREN. Because their advantage is that they ordered all the long lead time power generation items way in advance and got all the permits before hand, but they are losing out this edge due to Chips being delivered way slower than they can build. Hold up to VR, will cost shareholders big dilution risk assuming VR only gets delivered H2 2027 (H1 is just overly optimistic, until HVM starts for VR, any talks about pulling it in is pointless). What are your thoughts on how IREN is going to scale for the next 6 months? Just completing H1-4 for MSFT for GB300s and some air cooled B300s for Canadian and Childress? Or it's just going to be a much slower buildout into 2027?
Yep, people being fooled by Jensen Huang π€£. When MFG starts it's not true High Volume Manufacturing (HVM). For every new tech node TSMC and HBM will have to start production with bad yield and rush to improve the yield to achieve HVM. As to what % yield constitutes as HVM is proprietary to TSMC. Often takes at least 6 months - 1 year before the yield improves significantly resulting in ability to increase production. Hence, in general, GB300s will be produced more due to better yields from mfg improvements. I think delaying any contract signing to wait for VR is a mistake. Because as you pointed out, even if IREN does manage to secure a deal with the HS for VR, the time it takes for VR to be delivered on a large scale and to be monetised will be likely Q3/4 2027. More deals need to be signed before hand, so it can give IREN the optionality to pursue monetising part of their MWs to sign deals for VR. The flywheel needs to start turning faster, from new deals.
Agrees the biggest concern is GPU deliveries being the current bottleneck. If it is pushed out to 9+ months due to HBM shortages, it will impact time to revenue, heavily eroding IREN's advantage of having power now. If HS are all ordering VR300s in H3/4 2026 and it's pushed to 12 months, IREN will face serious delays in bringing the flywheel up. Even current B300 orders, we don't even know the timeline. Delivery starting from H2 could very well mean initial shipment starting only in Nov, through Jan and Mar resulting in full revenue taking 10+ months to even see anything, delaying the flywheel. I'm hoping for IREN it's much faster, but nothing in the HBM space indicates otherwise. VR + TPU + AMD demand in H2 2026 is just going to make everything worse. Initially, I felt one of the advantages IREN had was that they could sign colocation deals fast (end 2025/Jan 2026) and the HS would be able to get into the GPU queues earlier and it can evade the entire GPU delivery shit show that will only get worse.
So $WULF will get some power, that's great. +11.53% in pre-market.
I wish there was another company that would get more power. Too bad the PSO doesn't disclose their customer names!
Oh well!
Wen deal?
I was looking for Micron new sites, seems sites in Boise, Idaho is only coming online in early 2027, and other sites in Taiwan and Japan are only coming online in late 2027. That means we should see HVM for Boise earliest in H2 2027 and H1 2028 for other sites. Hynix seems more promising with a mega HBM Fab (Cheongju M15X) getting online in Q1 2026 (2027 HVM), and 2 more sites in 2027 (2028 HVM). Seems like 2028 will be year production really kicks up a notch to meet demand.
In general greenfield fabs take around 3+ years to build and be operational, (0.5-1 years for land permits/acquisition, 1.5-2 years for construction even with pre fab building materials, another 0.5-1 years for actual qualification of all the required equipments). Best case would be expansion on existing sites, if the clean room is already built, maybe 1 to 1.5 years before additional capacity is added. If it's greenfield sites, we are looking at 3 year delay for additional capacity being brought online. I have personally been involved in quite some greenfield sites, and a common problem in the past, is that when fabs actually bring the sites online, the economy has shifted and demand waned, results in the new fabs being underutilized. I think that's what has caused the memory fabs to be so slow to ramp up capacity in general. If demand for AI chips and HBM only increase, then I think we will have a bottleneck for the next 3-5 years for HBM production with just Hynix and MU. If Samsung is qualified and chosen as a HBM supplier for HBM4, that might help to ease some of the supply bottleneck. Important to continue observing the space.
Good plan to diversify! I have been contemplating too on when to diversify out of my 100% IREN port. Question would be diversify when IREN hits $120-140 (next big run) or by 2026/2027 when IREN hits $200+ when institutions start to rerate the company for more of it's power assets and potential AI DC revenues.
I must have been asleep when I typed my previous comment. I meant your portfolio was going to grow to 8 figures in 2 years time! $250 IREN by 2027 EOY isn't far stretched at all, slightly conservative! I'm in the same boat as you, engineer who all-in IREN! To me it's the conservative play, only buy what you have true conviction in, index buying only means you have conviction that the US govt is printing the world into oblivion.
The pace of progress at Childress is accelerating!
Just months after breaking ground, Horizon 1 electrical and mechanical works are well underway, Horizon 2 data halls are rising, Horizon 3-4 civils have commenced, and more than 1,200 workers are active on site bringing this next wave of AI infrastructure to life.
All of this keeps us firmly on track to deliver GPU superclusters for @Microsoft throughout 2026!