LEAD (https://t.co/Z9ZB7C59Ek) is delivering another successful project as it approaches the completion of the FDOT District 4 I-95 / Copans Road Interchange Improvements project in Pompano Beach, FL.
LEAD (https://t.co/Z9ZB7C5HtS) celebrates the beginning of the new year with the start of its new project, the FDOT D6 SR 90 (SW 8th St.), which includes safety improvements, intersections, drainage reconstruction, and resurfacing of nearly 5 miles of this landmark Miami street.
LEAD is on the final stretch to complete the FDOT D4 I-95/Copans Road project. The last barrier wall is getting poured today to switch traffic into final configuration in the upcoming days. Kudos to the entire project team!
#ontimedelivery#safetyfirst#quality#bestservice
Work with a view! LEAD’s night shift crews continue their hard work at the FDOT Henry Kinney Tunnel/Las Olas project. LEAD’s project team is making significant progress both on the Las Olas Plaza as well as inside of the Henry Kinney Tunnel.
#Dedication#Projects#Construction
The Underline Phase 2 project recent held its mass safety meeting. Safety always comes first at LEAD (https://t.co/Z9ZB7C5HtS). LEAD's team members carry their day to day duties with the strong belief, tools and training to prevent every accident.
#Safetyfirst#Safety
The LEAD (https://t.co/Z9ZB7C5HtS) team is rapidly advancing towards successfully delivering the Underline Phase 2 Design Build project for the Miami Dade Department of Transportation and Public Works. T
#LEAD#BestService#People#Integrity#Innovation#Excellence#Underline
The LEAD team (https://t.co/Z9ZB7C59Ek) is installing 24 precast concrete beams, 62.5 FT long and weighing up to 88,000 LBS, as it builds the extension of the Henry Kinney Tunnel and creates the platform for the new Plaza around the Las Olas Boulevard in Fort Lauderdale, FL.
We are honored and thankful to the FTBA and the FDOT for this recognition and congratulate the entire project team on obtaining the coveted 2022 FTBA Best in Construction Award - Design Build Category. The LEAD team consistently delivers the Best Service!
#lead#bestservice
LEAD (https://t.co/Z9ZB7C59Ek) is on the final stretch to deliver another successful project as it approaches the completion of the FDOT District 4 I-95 / Copans Road Interchange Improvements project in Pompano Beach, FL #transportation#interchanges#construction#bestservice
The LEAD (https://t.co/Z9ZB7C59Ek) team is making solid progress on the construction of the FDOT State Road 5 (US-1) from SR 862 (I-595) to SR 842 Broward Boulevard Project. #constructionnews#bestservice#leadership
The LEAD (https://t.co/Z9ZB7C59Ek) team is making solid progress on the Underline Phase 2 design build project being performed for the Miami Dade Department of Transportation and Public Works and Friends of the Underline.
The LEAD (https://t.co/Z9ZB7C59Ek) team is making solid progress on the construction of the FDOT State Road 5 (US-1) from SR 862 (I-595) to SR 842 Broward Boulevard Project. Kudos to the entire project team, a true partnership of the FDOT, CEI, EOR and LEAD's team members.
Today, we celebrated at the groundbreaking ceremony for the Underline Phase 2 project. Blessed to have State of Florida, Miami-Dade County and City of Miami leadership supporting Meg Daly’s Friends of The Underline initiative and attending the ceremony.
LEAD (https://t.co/Z9ZB7C59Ek) was honored by the Cuban American Association of Civil Engineers (CAACE) with the 2021 Special Project Award for the delivery of the state of the art Golden Glades Multimodal Transportation Facility project.
For the second year in a row, LEAD (https://t.co/Z9ZB7C59Ek) has been recognized by the prestigious South Florida Business Journal as one of South Florida’s Fastest Growing Companies. We look forward to continued growth by consistently providing the Best Service.
LEAD (www.LEAD-EC.con) looks forward to delivering another successful design-build world class project in our community as described in the Miami Herald article shown below and published this week.
https://t.co/RBEQNYvWx6
The LEAD (https://t.co/Z9ZB7C59Ek) team is starting the construction of the FDOT State Road 5 (US-1) from SR 862 (I-595) to SR 842 Broward Boulevard Project. LEAD's team looks forward to continue delivering the Best Service!
LEAD remembers and honors the 9/11 victims. For younger Americans, 9/11 is no longer an experience lived but history learned. We encourage this generation to understand the hope, resiliency, and unity with which we responded and which can lift us up as a nation
#neverforget911