September 3,2025
Meeting highlights
Discussed changes to 248CMR sections 3 and 11
Portland Loo possible not access at night, no hot water and non compliant in other areas
4800sq’ building requiring 2-1/2 baths
Denied use of “air inlet device”, suggested using “bow venting”
Tabled a decision on use of composting toilet not on product approved list
Discussion of section 3 pertaining to inspectors denying permits for unpaid taxes
Meeting adjourned 1:24
August 6, 2025 meeting highlights
Discussion on the use of a copper p trap utilizing press technology between copper pipe and fitting
Variance requests approved for plumbing fixture distance greater than allowed by 10.10 (15)18.Also, allow construction of new buildings utilizing restroom in separate building per 10.10 (15)18 a.
Variance request denied for use of a “drum trap” during a kitchen renovation.
Meeting adjourned 10:40 AM