Dear Martín: the bottleneck isn’t “power,” it’s the interconnection queue and cost allocation. FERC didn’t add a single MW — it touched tariffs and study timelines via §206 show-cause orders, precisely to dodge the NOPR and the very lawsuits you’re worried about. And the detail you missed: the largest data center hub sits in Texas/ERCOT, outside federal jurisdiction entirely. The US doesn’t have “a” grid or “a” regulator. The real lever is flexible load + co-location — the load adapts to the grid, not the other way around.