NOTICE OF ONGOING MAINTENANCE AT 132/33kV DELTA TRANSMISSION SUBSTATION
The Transmission Company of Nigeria, TCN, Delta Sub-Region, wishes to inform the public that the ongoing preventive maintenance at its Delta 132/33kV Transmission Substation, which commenced yesterday, 4 June 2026, is progressing as scheduled. The work will continue daily from 10:00 a.m. to 5:00 p.m. until 16 June 2026.
The maintenance is to facilitate the connection of a bus coupler circuit breaker and the rehabilitation of five isolators on the main busbar.
Consequently, 33kV feeders emanating from transformers at Effurun and Delta 132/33kV Transmission Substations, including Effurun, Warri, Sapele, Osubi, PTI, PMSL, Refinery I, Refinery II, and Enerhen feeders, as well as Isoko/Kwale, Otovwodo/Patani, Ughelli/Shell, Agbarho/Eku, Aladja, Imoniyame, and Beta Glass feeders, will be out of service during the maintenance period.
However, power supply will be restored daily at 5:00 p.m., enabling Benin DisCo to offtake electricity for its customers, following the completion of each day’s maintenance activities.
TCN apologizes for every inconvenience caused by the ongoing maintenance exercise.
Ndidi Mbah
GM, Public Affairs
5/6/26
Load Allocation | 07:03:00
Abuja disco - 567MW
Benin disco - 239MW
Eko disco - 478MW
Enugu disco - 229MW
Ibadan disco - 354MW
Ikeja disco - 560MW
Jos disco - 146MW
Kaduna disco - 163MW
Kano disco - 174MW
PH disco - 206MW
Yola disco - 77MW
Total - 3,193.00MW
Load Allocation | 22:36:00
Abuja disco - 599MW
Benin disco - 253MW
Eko disco - 506MW
Enugu disco - 243MW
Ibadan disco - 374MW
Ikeja disco - 592MW
Jos disco - 146MW
Kaduna disco - 163MW
Kano disco - 174MW
PH disco - 218MW
Yola disco - 77MW
Total - 3,345.00MW
Load Allocation | 21:53:00
Abuja disco - 619MW
Benin disco - 261MW
Eko disco - 523MW
Enugu disco - 251MW
Ibadan disco - 387MW
Ikeja disco - 612MW
Jos disco - 146MW
Kaduna disco - 163MW
Kano disco - 174MW
PH disco - 226MW
Yola disco - 77MW
Total - 3,439.00MW
Load Allocation | 16:35:00
Abuja disco - 580MW
Benin disco - 307MW
Eko disco - 489MW
Enugu disco - 296MW
Ibadan disco - 455MW
Ikeja disco - 573MW
Jos disco - 149MW
Kaduna disco - 173MW
Kano disco - 178MW
PH disco - 269MW
Yola disco - 50MW
Total - 3,519.00MW
NOTICE OF ANNUAL MAINTENANCE ON 40MVA 132/33kV TRANSFORMER AT IWO TRANSMISSION SUBSTATION
The Transmission Company of Nigeria (TCN), Osogbo Region, hereby notifies the public that routine annual maintenance will be carried out on the 40MVA 132/33kV power transformer at the Iwo Transmission Substation today, 4th June 2026, from 10:00am to 5:00pm.
The maintenance is part of TCN’s ongoing efforts to ensure the reliability and efficient operation of the transmission network.
Consequently, Ibadan Electricity Distribution Company (IBEDC) will be unable to off-take electricity to its customers in Iwo Town, Bowen University and Rabbish for seven hours only.
TCN apologises for any inconvenience this will cause electricity consumers in the affected areas.
Ndidi Mbah
GM, Public Affairs
4/5/26
#tcnnigeria
#electricity
Load Allocation | 06:34:00
Abuja disco - 619MW
Benin disco - 328MW
Eko disco - 522MW
Enugu disco - 316MW
Ibadan disco - 486MW
Ikeja disco - 611MW
Jos disco - 142MW
Kaduna disco - 165MW
Kano disco - 170MW
PH disco - 287MW
Yola disco - 74MW
Total - 3,720.00MW
Load Allocation | 18:27:00
Abuja disco - 656MW
Benin disco - 277MW
Eko disco - 554MW
Enugu disco - 266MW
Ibadan disco - 410MW
Ikeja disco - 649MW
Jos disco - 143MW
Kaduna disco - 160MW
Kano disco - 171MW
PH disco - 239MW
Yola disco - 76MW
Total - 3,601.00MW
Load Allocation | 16:09:00
Abuja disco - 604MW
Benin disco - 255MW
Eko disco - 510MW
Enugu disco - 244MW
Ibadan disco - 377MW
Ikeja disco - 597MW
Jos disco - 143MW
Kaduna disco - 160MW
Kano disco - 171MW
PH disco - 220MW
Yola disco - 76MW
Total - 3,357.00MW
SIX TCN TOWERS VANDALIZED ALONG APIR–LAFIA 330KV TRANSMISSION LINES
The Transmission Company of Nigeria, TCN, wishes to inform the public that six transmission towers, from T125 to T130, on Apir–Lafia 330kV Transmission Lines I and II have been vandalized.
The collapse occurred at about 1:15 a.m. on 30th May 2026, during a heavy downpour. Trial reclosure of these line II was made at 2:08 am following the initial tripping and failed.
The tripping of lines prompted a physical line trace to determine the fault which revealed damage to critical components of towers T125 to T130, confirming acts of vandalism on the affected sections of the transmission corridor.
As a result, both Apir–Lafia 330kV Transmission Lines I and II remain out of service pending reconstruction of the affected towers. TCN engineers have been mobilized to site to assess the extent of damage and ascertain materials required to commence to restore normal transmission along the corridor.
Meanwhile, the Lafia 330kV Transmission Station is being supplied through the Lafia–Jos transmission line as a temporary measure to minimise the impact of the outage on affected electricity customers within the franchise areas of Abuja Electricity Distribution Company (AEDC) and Jos Electricity Distribution Company (JEDC).
TCN strongly condemns the continued vandalism of power transmission infrastructure as it undermines years of investment in the sector.
We appeal to host communities and the general public to remain vigilant and report any suspicious activities around transmission installations to security agencies or the nearest TCN office. Collective action is essential to protect national grid assets and ensure reliable power supply.
Ndidi Mbah
GM, Public Affairs
3/6/26
#tcnnigeria
#electricity
#vandalism
Load Allocation | 11:31:00
Abuja disco - 601MW
Benin disco - 254MW
Eko disco - 508MW
Enugu disco - 243MW
Ibadan disco - 376MW
Ikeja disco - 595MW
Jos disco - 143MW
Kaduna disco - 160MW
Kano disco - 171MW
PH disco - 219MW
Yola disco - 76MW
Total - 3,346.00MW
Load Allocation | 06:27:00
Abuja disco - 635MW
Benin disco - 336MW
Eko disco - 535MW
Enugu disco - 324MW
Ibadan disco - 498MW
Ikeja disco - 627MW
Jos disco - 142MW
Kaduna disco - 165MW
Kano disco - 170MW
PH disco - 295MW
Yola disco - 74MW
Total - 3,801.00MW
Load Allocation | 22:08:00
Abuja disco - 642MW
Benin disco - 340MW
Eko disco - 541MW
Enugu disco - 327MW
Ibadan disco - 504MW
Ikeja disco - 634MW
Jos disco - 142MW
Kaduna disco - 165MW
Kano disco - 170MW
PH disco - 298MW
Yola disco - 74MW
Total - 3,837.00MW
Load Allocation | 21:49:00
Abuja disco - 621MW
Benin disco - 329MW
Eko disco - 523MW
Enugu disco - 316MW
Ibadan disco - 487MW
Ikeja disco - 613MW
Jos disco - 142MW
Kaduna disco - 165MW
Kano disco - 170MW
PH disco - 288MW
Yola disco - 74MW
Total - 3,728.00MW
Load Allocation | 19:19:00
Abuja disco - 654MW
Benin disco - 346MW
Eko disco - 552MW
Enugu disco - 334MW
Ibadan disco - 513MW
Ikeja disco - 646MW
Jos disco - 142MW
Kaduna disco - 165MW
Kano disco - 171MW
PH disco - 304MW
Yola disco - 74MW
Total - 3,900.00MW
Load Allocation | 16:22:00
Abuja disco - 668MW
Benin disco - 282MW
Eko disco - 564MW
Enugu disco - 270MW
Ibadan disco - 417MW
Ikeja disco - 660MW
Jos disco - 143MW
Kaduna disco - 160MW
Kano disco - 171MW
PH disco - 243MW
Yola disco - 76MW
Total - 3,654.00MW