February 2024 update for Luma Park Views project:
⠀
- Excavation works 80%
- Pile head breaking 80%
- PCC 50%
- Pile caps 30%
- Ground floor verticals 10%
⠀
Construction progress is on track.
December 2023 update for Luma22 project:
⠀
- Floor tiles on all floors 50%
- Plaster works on all floors 100%
- False ceiling 50%
- Roof waterproofing 50%
- External plaster 50%
⠀
Construction progress is on track.
November 2023 update for Luma22 project:
⠀
- Block works on all floors 100%
- Floor tiles 90% on G floor
- Plaster works on all floors 75%
⠀
We have conducted independent inspection with RERA and reached 52.85%
⠀
Construction progress is on track.
Our secret sauce?
⠀
In-house mastery at every crucial development stage, ensuring quality that speaks for itself.
⠀
Discover why our projects are more than just structures.
October update for Luma Park Views project:
⠀
- Fencing is completed
- Piling equipment is mobilized
- Mobilization completed
- Shoring beam installation is completed
⠀
Construction progress is on track.
October update for Luma22 project:
⠀
- Concrete casting works in all floors 100%
- Block works for 2nd and 3rd floors 100%
- Plaster works for 1st and 2nd floors 100%
⠀
The gym in the middle of the garden is now visible.
⠀
Construction progress is on track.
We are glad to announce that construction of the Luma21 project is complete. Authority handing over is under process, and we will be inviting our clients to join us on this momentous occasion.