@KimChiSpicey Do you know when all these contributions went out? I wonder how cluster they are and also how close it was to when the hit job on Jensen started.
@Ric_RTP What is wrong with you? Elon is giving something to these accounts. Even if it goes to zero, it doesn’t cost anybody anything. Would you rather that he not do it and this way these accounts get zero? Or would you rather you or the govt have the authority to tell him what to give?
@cremieuxrecueil As anyone come out and said this was true? Surely someone who has left NVDA can come forward. Otherwise it’s hearsay like the NYT/WSJ/WAPO sources
@EdSealing Asked AIs if Alice H was a spy & if Jensen aided the export of GPUs banned by law to China? All answered no. So why haul in Jensen for questioning? they believe AI is so strong they want control of it but don’t believe it when it suits them. Govt wants Narrative control.
@Stonefoxcapital Real question , what exactly did the CFO do to block the return of Jensen? All her prior statements in regards to his return were what the BoD stated.
@MilkRoadAI so why are boxes of hooper GPUs unopened and in Malaysia or Singapore and not in China? Why is China preventing the importation of these GPUs into its country.
Maryland families have been paying for Virginia's data centers on their power bills for over a year now. One Virginia county collected $1.2 billion in taxes off those data centers in a single year.
So when Maryland finally got offered a $5 billion data center of its own, 25,000 people signed a petition to kill it. Once you see the deal, you'd have signed it too.
Maryland and Northern Virginia share the same 13-state power grid, run by an outfit called PJM. Every year PJM holds an auction to lock in enough power for the hottest days, and the price went from $28.92 to $329.17 per megawatt-day in two years. The grid's independent watchdog says data centers caused 63% of the first jump. That's $9.3 billion, and it gets spread across everybody's electric bill, including in states that barely have any data centers. Maryland is one of them. The state's consumer advocate is now fighting another $1.6 billion or so at federal regulators over power lines built to feed Virginia.
Virginia's side of the deal looks a lot better. Loudoun County taxes the actual computers inside its data centers, $4.15 for every $100 of equipment. Those companies swap out servers every few years, so the county keeps taxing fresh hardware over and over. Data centers now cover 39% of Loudoun's budget, and homeowners there pay 80.5 cents per $100 on their houses, down from $1.145 a decade ago.
Maryland wrote the opposite rule. In 2020 the state let counties cut the tax on data center equipment all the way to zero, and Prince George's County passed its own version that November. A few months later the council made data centers by-right, which meant a project could go from application to shovels in the ground in 90 days without the council ever voting on it. One person signed up to testify against that bill. Everybody was stuck at home in the pandemic and barely noticed.
Here's what Landover was actually getting out of it. Back in 2021, the county's own economic development chief pitched a $500 million data center as worth about $66 million in property taxes over 10 years. At that rate a $5 billion campus should bring in something like $66 million a year. The developer's booklet for this one projected $13.7 million.
So picture living a mile from that lot. Your power bill has been climbing to cover data centers in another state. Now an 820-megawatt one is getting approved down the street with no council vote, in a county that already passed a law that could let it off the hook for the biggest tax it would owe, and it's promising about a fifth of what the county's own math said it should pay. I get why people signed.
The sad part is the land is still sitting there. The mall closed in 2002 and came down in 2006. The Commanders' stadium right across the road empties out when the team moves back to D.C. in 2030, and they've agreed to tear it down within 90 days of their first game at the new place. Prince George's is looking at a projected $151 million deficit and could end up with two giant empty lots staring at each other.
Loudoun proved a data center can pay for a big chunk of a county's schools and knock down everyone's property taxes. That only works when the county actually taxes the servers and the power bill doesn't land on the neighbors. Fix those two things and the next lot in Maryland probably gets built.