@Ramesh_2828@V_Senthilbalaji@TANGEDCO_Offcl Thanks for approaching us.The current will not pass through the water in case of opened sleeve as the cable not yet https://t.co/ZcgIGFKCe1 of now this SWD work is not yet completed . Hence,the cable will be charged only when all works of SWD were completed.
EE/TANGEDCO/AVADI.
@Arun321321321 @TANGEDCO_Offcl Thanks for approaching us.On site inspection it was found streetlight switch was defective .The same has been informed to concerned Avadi corporation official to attend to the complaint.
EE/TANGEDCO/AVADI
@Venkad@TANGEDCO_Offcl powercut occured due to 11KV feeder tripped@Avadi SS.On patrolling 11KV lines during heavy wind and rain,all switches were closed one by one and identified as PT insulator fault at tail end DT of Vaigai street and same replaced by new and power resumed early.
EE/AVADI
@Venkad@TANGEDCO_Offcl Power cut due to 11KV feeder tripped @Avadi ss.On patrolling the 11KV lines during wind and rain identified the PT insulator flash over at the tail end of Vaigai 100KVA DT.Replaced it by new one and supply restored at early.
EE/AVADI
@MsCrpcGlfRti@RajeshLakhani69 Entire stretch of LTline is strong by 7/2.59 conductor and there are no joints in the street. LT poles couldnot be shifted as per the request as there are objection from neighbour.pole at corner of street couldnot be shifted as LT lines will foul on neighbouring houses.
EE/AVADI
@zuhaibhussaink3 @sechennaicentrl @Avadi_Nasar@mkstalin@V_Senthilbalaji We are in receipt of your power interruption complaint near Avadi checkpost.
But though we want to settle the issue in response to your complaint,we are unable to locate your address or mobile number or service number to reach you.
please do anyone.
Thanks.
EE Avadi TANGEDCO