@nagaraju_patnam@GHMCOnline@CommissionrGHMC@KTRTRS Sir,The road was excavated by HWSSb for laying new drainage line .New Road got sanctioned and entrusted to the agency . Yesterday, foundation stone for the above work was laid by Honble MLA Madhavaram Krishna Rao( Kukatpally) Garu and work will be commenced soon.
Regards,EE30
@ArunBee@GHMCOnline Swach Namaskaram sir,
The said complaint pertains to secunderabad cantonment board (SCB).Now there is no stagination.
Regards,
EE30.
@RamacharyRachak@KTRTRS Sir,
During the work of construction of box drain,an old drain identified under neath metro rail bridge near Gurudhwara, Secunderabad .The agency started yesterday to construct catch pit at the opening without using protective things though instructed before staring of work.
@RamacharyRachak@KTRTRS Swach Namaskaram,
During the work of construction of box drain,an old drain identified underneath metro rail bridge near Gurudhwara, Sec'bad .The agency started yesterday to construct CP at the opening without using protective things though instructed before staring of work.
@nagaraju_patnam@GHMCOnline@KTRTRS Sir ,In response to the tweet, the formed pothole at manhole was filled with gravel and rectified temporarily.
Regards EE 30
@mahesh131615@GHMCOnline@KTRTRS @MinIT_Telangana Sir,
Desilting of park lane Nala is in progress.However stagination will be cleared with department labours.
Regards,
EE 30
@CitizenOIndia@KTRTRS Sir, in response to the tweet, the work is sanctioned for a length of 80m and estimated cost of Rs 13.00lakhs and due to non response of tenders,second time tenders were called for and is in tender process.after allotting to the agency the work will start immediately.