(2/2) With a warm and sunny spell forecast over the coming weeks, weโre fully prepared for the increase in aquatic weed growth and bloom activity that comes with it.
Looking forward to another busy season helping keep Londonโs waterways clear, safe, and navigable.
(1/2) Let the clearing commence!
We have officially started the 2026 weed season across the London waterways network.
Our boats are now positioned around the network & the team has already cleared the first patches of floating pennywort, floating weed & rubbish from key areas.
(3/3) We then had the delicate operation of breaking through into the round brick culvert without causing significant collapse or damage.
Works were completed successfully - see the photos below.
(2/3) Due to the remote location all materials and plant (including an 8t digger) had to be floated to site to lift the trench shoring and manhole rings into position.
(1/3) Need a tricky manhole installing? We are your team!
An old brick culvert which is still integral to water management along the Shropshire Union canal needed a new manhole constructing to facilitate safe inspection.
The never ending project! Works to Kegworth deep lock seemed never ending after freezing temperatures & then flooding disrupted the works programme by 2 months. Repairs were needed to repair the lock gates where significant leakages were noted from missing or rotten lock timbers.
Up creek with a paddle! Dealing with dense vegetation and invasive species from water requires specialist kit & teams. These works will enable Paddle UK to keep on top of the invasive species, floating pennywort going forward.
(2/3) Over 5000 bricks were laid with heritage lime mortar and finished with a cast in situ concrete coper. Managing a busy towpath and moorings with significant access constraints meant floating plant was essential to help lift & store materials and plant during the works.
(1/3) Tight spot and 5000 bricks to move & lay by hand! A full canal wall rebuild was needed along a busy moorings. After dewatering with a horseshoe dam the collapsed masonry wall had to be broken out by hand before a new concrete footing installed.
(1/2) What happens to old lock gates? After working with CRT to lift and change the old lock gates for new, the old gates are taken for recycling and upcycling. The gates are stripped down and turned into furniture, mantel pieces or planks for flooring.
(1/2) Changing the Gate! Our 55ft hi-capacity crane boat with welfare was deployed to the Birmingham & Fazeley canal to change lock gates with CRT. The gates were loaded from Mancetter Wharf before being floated to site, with the old gates then collected for recycling.
(2/2) This involves using stop planks to drain down the lock & all associated temporary works including access, fencing, lifting etc. Our range of craft also helps provide stable working platforms, lifting assistance, welfare & material storage for works to be carried out safely.
(1/2)
Our specialist lock teams have been supporting CRT with lock repairs during the busy stoppage season. From replacing collars, to repairing cills and strengthening existing lock gates we have the expertise to survey, source and then fit all parts of the locks.
Piling with a soft edge! The bank was collapsing, taking the towpath with it, so L8 sheet piles were installed. This created a stable edge to rebuild the towpath. But, the โhard bank protectionโ had a soft twist with the addition of steel brackets to hold pre planted coir rolls
Our NATO pontoons with 8t digger and specialist grab were deployed to remove a sunken boat from the Fossdyke canal. The NATO pontoon provided the perfect stable working platform with its hydraulic jack legs, for the team to break up and remove the boat from the canal.
Our contracting teams have recently completed works to repair a concrete culvert & ditch along a busy footpath. The emergency works involved installing a temporary coffer dam ahead of casting new concrete aprons to several sections that had become undermined.