$KEEL What the market does not understand is why no lease has been signed, even if potential customers say they are still confident in the sites.
Trying to squeeze every penny from tenants is not constructive for long term relationships, especially when you want to keep building with them.
@CaptainKeel
$KEEL earnings call is around the corner.
- Moses Lake keeps progressing. On October 26, the structure of the data center was being erected, as KEEL shows on its website.
- According to the DEP remediation documents (Act 2), the buildings in Sharon must wait for the vapor intrusion re-evaluation before construction can start. The report that includes it is due by March 31, 2027.
- Alternatively, maybe the three deals are not Sharon, Panther Creek, and Moses Lake, but Moses Lake and the two buildings in Sharon (80 MW and 30 MW).
$KEEL earnings call is around the corner.
- Moses Lake keeps progressing. On October 26, the structure of the data center was being erected, as KEEL shows on its website.
- According to the DEP remediation documents (Act 2), the buildings in Sharon must wait for the vapor intrusion re-evaluation before construction can start. The report that includes it is due by March 31, 2027.
- Alternatively, maybe the three deals are not Sharon, Panther Creek, and Moses Lake, but Moses Lake and the two buildings in Sharon (80 MW and 30 MW).
$KEEL still no lease signed, but things are moving.
Moses Lake is already working on the site. I checked satellite images from Sept 26, and you can see the ground work.
Sharon got a draft permit from the state on Sept 10. They asked for 7 edits to the erosion-control plans, which look like drawing fixes and nothing against the project itself. Keel has to answer by Oct 10. Public comments are open and no hearing is scheduled yet.
Panther Creek also has a draft stormwater permit since July, and a second one for streams and wetlands is still under review. The public hearing was Aug 20. Air permits haven’t been filed yet.
So Sharon and Panther Creek are both waiting on final permits, but progressing.
The CEO keeps saying the remaining permits are engineering work, not political. At Sharon, DEP’s letter lines up with what he said: the 7 items are just engineering fixes. Panther Creek is mostly technical too, though DEP is still reviewing the wetland answers.
“At the moment, we have more compute capacity than we have demand [...]”
Ok @Gartner_inc, this is nonsense. We are *massively* compute constrained. Our portfolio companies are struggling to find capacity.
Full article here: https://t.co/NWeBwEaDdr
$KEEL DEPs Sept 10 deficiency letter (issued along with the draft permit) was answered by Keel on Sept 18.
The 30-day comment period on the draft permit ends around Oct 26, and DEP can extend it by 15 days. The earliest realistic timing for a final Sharon permit is November 2026.
$KEEL still no lease signed, but things are moving.
Moses Lake is already working on the site. I checked satellite images from Sept 26, and you can see the ground work.
Sharon got a draft permit from the state on Sept 10. They asked for 7 edits to the erosion-control plans, which look like drawing fixes and nothing against the project itself. Keel has to answer by Oct 10. Public comments are open and no hearing is scheduled yet.
Panther Creek also has a draft stormwater permit since July, and a second one for streams and wetlands is still under review. The public hearing was Aug 20. Air permits haven’t been filed yet.
So Sharon and Panther Creek are both waiting on final permits, but progressing.
The CEO keeps saying the remaining permits are engineering work, not political. At Sharon, DEP’s letter lines up with what he said: the 7 items are just engineering fixes. Panther Creek is mostly technical too, though DEP is still reviewing the wetland answers.
Chilean Pension Funds annihilated after betting U.S. Treasury Yields would continue to go down over the past 2 years 🚨 Now racing to close out their positions 👀
$KEEL still no lease signed, but things are moving.
Moses Lake is already working on the site. I checked satellite images from Sept 26, and you can see the ground work.
Sharon got a draft permit from the state on Sept 10. They asked for 7 edits to the erosion-control plans, which look like drawing fixes and nothing against the project itself. Keel has to answer by Oct 10. Public comments are open and no hearing is scheduled yet.
Panther Creek also has a draft stormwater permit since July, and a second one for streams and wetlands is still under review. The public hearing was Aug 20. Air permits haven’t been filed yet.
So Sharon and Panther Creek are both waiting on final permits, but progressing.
The CEO keeps saying the remaining permits are engineering work, not political. At Sharon, DEP’s letter lines up with what he said: the 7 items are just engineering fixes. Panther Creek is mostly technical too, though DEP is still reviewing the wetland answers.
$aib has signed a deal with $nbis even before $keel secured its own, although the price dropped after the announcement.
Let's see if $keel signs any deals next.
$AIB seems to be losing momentum. Still no deal in sight.
The COO, ex- $NBIS, resigned under a separation agreement.
However, CLT-01 and the MN site seem to be moving forward, with permits progressing.
Let’s see if they can close a deal in the second half of this year.
$AIB seems to be losing momentum. Still no deal in sight.
The COO, ex- $NBIS, resigned under a separation agreement.
However, CLT-01 and the MN site seem to be moving forward, with permits progressing.
Let’s see if they can close a deal in the second half of this year.
It feels like we're watching a new giant emerge.
$AIB has just uploaded its July Investor Presentation and confirms the following:
- 65 MW expected to be signed in the second half of this year
- 3 new lease signings in 2027, adding a total of 350 MW in contracts
Additionally, Jerry Tang, the CEO of AIB Data Centers, is now a member of the Forbes Technology Council.
$KEEL hires ex-Googler as VP of Data Center Program Delivery
In August, he started as KEELs VP of Data Center Program Delivery after previously leading hyperscale data center planning and execution at $GOOG, driving cross-functional partner agreements and developing custom pre-construction solutions to rapidly scale infrastructure.
$DELL ON AI INFERENCE DEMAND:
“Inference has passed training and is pure demand on our industry”
Dell expects inference token demand to grow 87x to 3,600 quadrillion tokens by 2030, while training demand grows 5x
“Enterprise agentic to be the single largest workload by 2028”
$IMSR
> VP of Projects hired in June for projects at the TA&MU RELLIS Campus (ex-US Naval Officer)
> TEFLA Lead hired in May. His previous experience was in the Fuel Cycle and Materials Laboratory at Texas A&M University
> On August 17, an email from the NRC was released accepting the Postulated Initiating Event document. This was announced in the Q2 earnings call.