Non ascoltate me, ascoltate @repubblica - forse sarebbe ora che nPlan si attivasse anche in Italia per prevenire altri disastri? Per non parlare del ponte sullo stretto...
https://t.co/ZsboRG50EA
Dylan Patel: always-on agents went from 0 to 45% of SemiAnalysis's AI spend in 10 months.
Anything that trades while you sleep gets a risk limit and a kill switch before it gets a budget.
In AI, agents are getting the budget first.
People ask how I did a PhD in deep learning theory while working as a quant.
Badly. Slowly. Every weekend, for years.
'Brick by brick' isn't a motivational poster. It's a calendar you don't skip.
OpenAI now calls its data centres "Compute Campuses".
Fitting. Lambda says its $33bn Alabama campus takes up to five years to build.
In Italy, students who finish late are "fuori corso". 77% of data centre projects are already behind plan at their first update. Fuori corso.
@collision@sama Best question of the episode, and we have the data.
Across 750,000 past schedules, 88% of data center projects hit delays before the foundations are poured. 60% slip 3+ months.
It isn't permits or labour. It's execution. Robots inherit the same plan.
https://t.co/pQMVHm8UIW
Sam Altman says your PC's RAM idles at 5% and belongs in his data centre.
By that logic my golf clubs, idle for the 20 years I rage-quit, belong at Francesco Molinari's house.
I need to work on my short game more.
Delay gets baked in years before anyone gets a layoff letter. Fix the critical path, not the org chart.
Full study: https://t.co/QF5RJyMMVZ
Independent, public data only. No involvement or endorsement by Disney.
Disney: find 20% savings.
Also Disney: ~$9bn a year of capex, inside a ~$60bn parks plan.
The real money isn't in headcount. Shave 1% of overrun off that plan and you've found $600m. 🧵
We rebuilt the schedule for Piston Peak, the Cars land at Magic Kingdom, from permits and aerial photos only.
Our plan: 14 Mar 2030
Forecast P50: 24 Feb 2031, 347 days late
Chance of on time: 1%
Half the slip lands after the mountain is done: ride testing and certification.
The @TheB1M did a video about the Hard Rock guitar hotel in Vegas. Completely forgot to mention that they already built one in FL before they even owned the land from the Mirage. And it worked so well in FL that they decided to hire the same architects and reproduce it but bigger
Free 17-page study and plan file: https://t.co/SpHCktIP4X
Fully independent, public data only. No involvement from or endorsement by OPG or its partners.
OPG announced Darlington Unit 1 as 142 days early. It finished 44 days after its working plan.
Both are true. OPG keeps three dates and announces against the public one, which held 4-7 months of buffer.
Fine on a job you've done four times. Not on a first-of-a-kind SMR.
We forecast the new Darlington SMR from public filings only.
Public date: end 2030, ~9 months of buffer.
Most likely date we see: August 2032.
Six decisions can win back ~9 months. Four are due before 1 Dec 2026.
If you report progress, ask which date you're early against.