@JigarShahDC Where are you seeing 4h BESS built for $500k per MW? I agree BESS are likely the fastest, cheapest way to add capacity even at diminished ELCCs, but the capex is a lot higher than that
@ShanuMathew93@nytimes This data probably reflects tech companies liquidating wholesale power from any physical PPAs procured for the RECs, not delivering to retail load. The volume is also a small subset of their total procurement, likely because many PPAs are REC-only or settle financially
@apoorv_bh89@_HannahRitchie *And the cost of past/future fires from that delivery. And other nonbypassable charges for policy initiatives. There's a lot bundled into rates, especially in CA
@AriPeskoe PJM is a consistent net exporter to neighboring markets like NYISO and MISO so some of that cost is billed to LSEs outside PJM. Probably reduces that ratio a little?
@TermPowerTrader@joesmyth@EnergyInnovLLC Obviously not all MWhs are equally valuable, so cost alone is an overly simple comparison. But you can construct a portfolio of solar and storage that beats most existing coal on cost for similar energy and capacity value in most markets now.
@TermPowerTrader@joesmyth@EnergyInnovLLC Maybe the hourly marginal cost of coal, which is mostly fuel. Factor in coal plant FO&M for a better comparison and solar starts to look cheaper. Then add sustaining capex for coal and it's even more expensive.
@benserrurier I think it depends on your use case. Utility IRP models use a wild range of assumptions from simple OTC hub prices to avg CAISO shapes to simulated dispatch or black box volatility functions. "Preferred" method often depends who is judging and what resource type they want to sell
@tommatzzie If we're trying to procure clean MWhs as efficiently as possible, I'd rather pay marginal MWhs equivalently and take what's cheapest. No inherent reason to pay Y5 solar MWhs more than Y6. Would incentivize premature repowering, inefficient overbuild of shortlived resources, etc
@tommatzzie What makes a clean MWh from a newer resource more valuable than a clean MWh from a legacy resource? Sure, there's a financial advantage to front-loaded incentives, but disconnecting incentives from the good they're meant to incentivize (clean MWhs) seems bad
@jdeely@BPBartholomew Not all battery capacity is following the same price signal. Optimal dispatch looks different for DA vs RT vs AS markets. Costs and operating constraints vary too
@jdeely @California_ISO I'll take the over for curtailment in 2022. Solar additions should swamp the impact of storage additions, but BPA joining EIM could help at least.
@cody_a_hill Global storage additions in 2019: 3 GW per IEA. CAISO storage additions in 2020-21: about 3 GW by eoy according to CAISO. Doesn't need to be a majority of production.
@cody_a_hill CAISO has ~150 GW of storage in the queue today, so what's the critical path bottleneck for 2024 COD? Is it just offtake? Interconnection agreements?
Always tough to reconcile CA's huge need for MW and similarly huge interest from developers.
@jdeely @California_ISO Would guess that YoY increase in load (at least since March) and EIM exports also factor into reduced total curtailment this year, but definitely hard to attribute anything in isolation
@cody_a_hill@SolarInMASS@karenstreet@jdeely@FordneyEnergy Yep, 700+ MW due online by end of Aug, mostly PV paired. Probably already at 1,000 MW interconnected but will take more than that to see 1 GW simultaneous export to CAISO even with high prices
@TimMLatimer In the proposal, it's an ELCC approach which would naturally weight the months with greatest reliability needs most heavily (i.e. August-September)
@TimMLatimer Planning for and appropriately crediting future resources is an important modeling effort and market design issue as the supply mix evolves and loads become more responsive. Lots of hard work going on around this topic right now.
@TimMLatimer Depends which resources get procured, which will have interactive reliability effects at that scale, so the exact answer is nontrivial. Based on today's crediting, 1 MW NQC = approx 1 MW gas or 4+hr storage, 1.2 MW geo, 3-6 MW solar or wind depending on the month