@ICMallikarjuna@KTRTRS Dear Sir, the work involves shifting of 132 kva Electrical cable, two drinking water supply pipe lines, sewer lines and communication cables also..initially it took lot of time to get this services shifted on to the edge. Kindly bear with the delay. Regards: S.E (M), SBZ..GHMC
@ICMallikarjuna@KTRTRS Respected sir. The work started 9 months ago. 90 % work is completed. Traffic is passing on this new bridge since 5 months sir. balance work will be completed in ten days.
Regards
@rahulbannatwala@KTRTRS Respected sir. The photographs depict milling done.... to maintain camber... . This is a prerogative sir... to avoid water stagnation on the road as well to reduce ever increasing road thickness. Road will be laid by 6th Nov sir. Regards.
@vedula_murthy@hmwssbgmom7@KTRTRS Sir. I have requested in person GM HMWSSB to take up the remodelling work. Will remind his higher ups tomorrow. Regards
@Naresh4HBK@KTRTRS Swacha Namaskaram sir. This road belongs to SCR. they neither lay the road not allow GHMC to do so. SCR has asked to pay Rs. 250 lacs towards wayleave charges. Commissioner sir GHMC approved this. Land acquisition wing following the payment process. once acquired... CC road..
@deepatejram contd... in front of Satya kidney centre. sir... by this month end... 1 mtr dia pipe line in street no 5 will be completed. Simultaneously CC road will be laid end to end sir. kindly bear with this inconvenience. na masthe.
@deepatejram Swacha Namashkar Ramanjaneyulu gaaru. Am concerned SE. Road no 5 , Himayatnagar is closed sir for facilitating laying of 1000 mm dia Rainwater drain. The main road is not cut since...weve laid pipe using Trench less technology. This work is intended to prevent water stagnation
@vedula_murthy@hmwssbgmom7@KTRTRS Swacha Namaskaram sir. Yes. Have brought this to the notice of our counterparts in HMWSSB. Will prevail upon them to rectify this problem as early as possible. regards
@vittuchitham @Krishna50911026 @KTRTRS@CommissionrGHMC Swacha Namaskaram sir. the trunk line carrying the industrial effluents from Patancheru is frequently overflowing. Intimated concerned industrial wing to desilt their line. ZC North has met them requesting immediate action.The road widening is being taken up by HRDC. Regards
@venkate49304674@KTRTRS Swacha Namaskaram sir. Venkatesh Garu.
am SE Secbd zone. This work is sanctioned. Agency / contractor has already commenced work in street no 5 West Maredpally. Due to inclement weather, progress is paused. We will cover roads of street no 1 also. it's just a matter of time.
@kesarisuresh @SriWelfare@KTRTRS@bonthurammohan@KTRoffice Swacha Namaskaram sir. Sanction for Rs.190 lacs given by Commissioner GHMC. Tenders are called. Receipt of tenders on 9.7.18.
will commence the work by 15th of this month. thanks
@AleemuddinMuhd@CommissionrGHMC@GHMCOnline@KTRTRS@bonthurammohan Sir. Tenders are received for laying CC ROADS in this stretech and adjoining lanes in Prakashnagar .. Begumpet. The tenders are under evaluation. Hopefully we will commence the work by 15th of this month. kindly bear with inconvenience. thanks