“The Beit Shemesh facility, designated as MDCIL-4, is already under construction, holds a grid connection approval, and features a maximum capacity of 135 megawatts IT, meaning the new agreement utilizes half of its capacity. The second facility, MDCIL-7 in Masmiya, is currently designated as land for future development, and its electricity connection application has been frozen by the Electricity Authority, making approval a formal condition for completing the transaction with Nebius. Mega Aor estimates the total construction cost for these facilities at approximately 1.6 billion dollars, calculated at 12 million dollars per megawatt of IT capacity.”