🚧 Ejipura Flyover Works Accelerated — Opening Targeted This Year!
The much-awaited Ejipura–Kendriya Sadan Flyover is now progressing at a rapid pace under the Greater Bengaluru Authority and Bengaluru South City Corporation.
👷♂️ Chief Engineer Dr. Raghavendra Prasad informed that the major flyover works are expected to be completed by October 2026.
✅ Long-pending St. John’s Portal Frame issue resolved in February 2026
✅ All foundation works completed
✅ 728 out of 762 segments cast
✅ Only 15 spans pending installation
✅ Main structure targeted for completion by October-end
The flyover is expected to open for public traffic within this year, bringing major relief to commuters and improving connectivity across the corridor. 🚗✨
#EjipuraFlyover #Bengaluru #NammaBengaluru #Infrastructure #GBA #BSCC #TrafficRelief #UrbanMobility #BengaluruDevelopment #GreaterBengaluruAuthority @DKShivakumar
@Ejipuraflyover Onward and upward! There are 23 spans remaining and if you take 10 days per span, like the last one, then you will need 33 weeks to complete. There are 36 weeks till the end of July 2026, the proposed completion of this flyover. Fingers crossed that the bills are cleared on time.