Sanctioned estimate. The catchpit is constructed as temporary measure so that water can receed.During rain due to some obstructions inside the catchpit the water logged for sometime and cleared by MET.For permanent solution,remaining 90 mtrs of roadneeds to be lowered and laid2/2
@sandeepsrao21@Kapra_dc7@MCMalkajgiri Dear citizen,
We regret the inconvenience caused.
The pending road is the storm water drain slab. The work for remodeling of Storm water drain is sanctioned and in tender process.
The work will start soon and the issue will be resolved.
Regards,
AE Kapra circle-7
MMC
@khanHyd7@GHMCOnline@gadwalvijayainc Dear citizen,
The road is excavated for remodeling of Storm water drain. The road will be restored once the work of drain is completed.
We regret the inconvenience caused
Regards,
AE Mallapur
Kapra circle, GHMC
@dev_raju@Comm_HYDRAA@GHMCOnline Dear citizen,
Inconvenience regretted.
Attended potholes with wetmix. As discussed potholes will be attended with BT shortly.
Regards,
AE Mallapur
Kapra circle-1, GHMC
@PoojaPootula@GHMCOnline@KTRBRS@TelanganaCMO Dear citizen,
We regret the inconvenience caused. Jungle clearance will be taken up and garbage will be removed in coordination with sanitation wing.
Regards,
AE Mallapur,
Kapra Circle-1, GHMC
@ammusrinivasrao@GHMCOnline@SunithaRasuri Sir/Madam,
Necessary openings are provided for free flow of storm water from opposite thirumala Appartments to VNR side. If any additional openings are required, will be provided.
Thanks,
AE, Mallapur
@ap9675868@GHMCOnline@CommissionrGHMC@gadwalvijayainc Sir/Madam,
The work for laying of storm water drain pipeline is in progress. Once the work is completed the debris will be cleared.
We regret the inconvenience caused.
Regards,
AE Mallapur
Kapra circle-1, GHMC
Sanctioned estimate. The catchpit is constructed as temporary measure so that water can receed.During rain due to some obstructions inside the catchpit the water logged for sometime and cleared by MET.For permanent solution,remaining 90 mtrs of roadneeds to be lowered and laid2/2
@VenuRed10875552@GHMCOnline Dear Citizen,
The roads are damaged due to laying of drinking water line by HMWS&SB. Estimate is submitted for laying of CC road and work will be started after availing administrative sanction.
The material dumped is by private house construction people.
Regards,
AE ward-4
@SrikanthKolanu1 @GHMCOnline Sir,
We regret the inconvenience caused. Temporary formation of road will be done shortly. However, estimate will be submitted for administrative sanction for laying of road.
Regards,
AE-Ward 4
GHMC
@SattarFarooqui@GHMCOnline@CleanNacharam Dear Citizen,
Sorry for the inconvenience caused. The pothole is due to the presence of water valve. The issue will be addressed shortly
Regards,
AE Ward-4
GHMC