Supply at 100KV Vasai EHV Substation resumed partially. 3 Feeders catering power supply ~1Lacs consumes have been charged. Rest work is in progress and power supply will be restored shortly..
All the 16 feeders have been restored now..40 Xmer from the 75 mentioned earlier are also restored..Remaining work under progress..Individual Xmer restoration is going on through proper checks...
Power has been restored in Vasai area. Thanks team MSEDC L and officers of MSETCL for doing exemplary work in adverse conditions. Also we appreciate the patience and cooperation of affected citizens.