@SuptAbad@JTMDAURANGABAD@ManishRAgrawal9@ceaurangabad proposed outage on 18.10.19 but as per letter from MASSIA/2019-20/MSCDCL/130 Dt.16.10.2019 we have not taken outage.After diwali festival we will continue maintainance work on remaining feeders to dige helthy and uniterrupted supply to indutrial consumer.
inconvenience regretted.
@SuptAbad@JTMDAURANGABAD@ManishRAgrawal9@ceaurangabad As per assurance in the Meeting with Hon JMD sir Auranagbad.we have taken walk down survey on all industrial feeder on date.10.10.2019 and 16.10.2019. and partial maintainance done on 11 KV inustrai-1,Ind-11,Radent Agro,Rama/N-1 feeder.and for reamining feeder maintainance we
@orthopod1274 @JTMDAURANGABAD@ceaurangabad@SuptAbad 3 meter in premises & connection is from UG cable from road cross mini pillar.due to heavy rain on sat this cable got punctured and faulty supply was restored primarily/temporary through other source on sunday.again on monday staff was https://t.co/OrR4a3tHwc availble at site.