STANDARD NUCLEAR HAS ALL THE LONG-LEAD MODULE EQUIPMENT IN HAND FOR TWO IDENTICAL TRISO FUEL PLANTS, ONE IN TENNESSEE AND ONE IN IDAHO.
CRITICAL PATH NO. 04: BUILT TWICE
· Standard Nuclear (NYSE: $STDN ) says construction is substantially complete at SN-TN in Oak Ridge, Tenn., and SN-ID in Idaho, two identical facilities that each start at up to 1 metric ton of uranium (MTU) of TRISO a year and are designed to scale to 2.5 MTU.
· All long-lead manufacturing-module equipment for both has been procured and is in hand. At SN-TN, module installation is ongoing, with most long-lead module installation already complete; at SN-ID, it will follow.
· Of the company's $577.2 million total contract backlog at Sept. 30, $443.5 million is purchase options under executed contracts, and the company says backlog is not a measure of contracted revenue.
From a buyer's seat, with the long-lead equipment in hand, the hardware no longer looks like the long pole; installation and DOE authorization do. The next signal is on the demand side: how much of that option-heavy backlog converts to firm orders as the new capacity comes online.
If you were buying TRISO for a first reactor, what would you need to see before converting an option into a firm order?
$STDN rated Buy at $15 by Goldman. Only pure-play fuel fabricator on the market.
Analyst "sees revenue jumping from $17.4 million this year to $368.9 million in 2028" 🔥
@SenSchumer Literally every 401K holder is long NVDIA by default if they own index funds. Are you saying Trump and billionaires are the only ones long and benefitting?
STANDARD NUCLEAR SUBMITTED FINAL DOCUMENTED SAFETY ANALYSES FOR TWO TRISO FUEL PRODUCTION FACILITIES, SIX DAYS APART. ONE TEMPLATE, TWO STATES.
THE SUBMISSIONS
· Standard Nuclear (NYSE: $STDN ) submitted final Documented Safety Analyses (DSAs) to DOE for both of its Hazard Category 2 (HC-2) fuel production facilities: SN-TN in Tennessee on November 6, 2026, and SN-ID in Idaho on November 12, 2026. Both submissions remain subject to DOE review and approval.
· DOE approved the Preliminary Documented Safety Analyses for both facilities in July 2026, and the SN-ID submission follows the same construct as SN-TN, reflecting the templated, replicable design of the two facilities.
· The company says securing DSA approval would mark a critical milestone and position it to fulfill existing 2027 fuel production orders.
The second submission is the real story. CEO Kurt Terrani @kterrani credits replicating an essentially identical facility design for near-simultaneous DSA submissions, the same standardization logic the industry is counting on for Nth-of-a-kind reactors. Per the company's November 12 earnings release, the remaining steps for SN-TN are DOE review followed by an Operational Readiness Review, and the company targets DOE authorization to operate both sites in February 2027.
@SenSanders Explain how spending is oligarchy when the money spent didn't yield the result he spent on? You're tweet is nonsense. Only thing you've ever built is personal wealth and discourse among those you govern. You have never created anything tangible that has created positive utility.
@NYCMayor They pass costs to the consumer. Take macro Econ 101. Coupled with micro 101 and you’re on your way to understanding your policies hurt consumers, not help.
@LeadingReport Has Pope Leo studied economics or existing systems? I’d be shocked if he understands ISLM models. Not sure that was covered in theology and philosophy.